• Fix the luminaire to a suitable solid surface using the wall plugs and screws provided
• Tilt so the cable entry points are accessible
• Unscrew the sealing nut from the compression gland (see Fig. 2) and fit it over the supply 
   cable

• Unscrew the main body of the compression gland from the fitting ensuring that the 
   hexagonal lock ring is not dislodged (see Fig. 2)
• Remove the protective insert from the compression gland, leaving the rubber gasket in 
   place (see Fig. 2), and pass the supply cable through the compression gland
• Prepare the supply cable as shown by stripping back the outer sheath and basic insulation 
   to the correct length (see Fig. 3)

Fig. 2

 

Fig. 2 

 

Unscrew the main body of the compression gland from the fitting, ensuring that the hexagonal lock ring 

is not dislodged (see Fig. 2) 

 

Remove the protective insert from the compression gland, leaving the rubber gasket in place (see Fig. 

2), and pass the supply cable through the compression gland 

 

Prepare the supply cable as shown by stripping back the outer sheath and basic insulation to the 

correct length (see Fig. 3) 

 

 

Fig. 3 

 

Connect the supply cable ensuring the correct polarity is observed: L - Live (brown), E - Earth 

(green/yellow), N - Neutral (blue). Please be aware that undue pulling or rotating of the termination 

block will cause damage to the fitting 

 

Tighten the compression gland and sealing nut ensuring a tight seal is made. Do not overtighten 

 

Tilt the fitting to the desired angle and tighten the nuts on the side 

 

Switch on and check for correct operation 

PIR / Microwave Sensor Accessory 

 

Isolate the mains supply to the fitting 

 

Remove the capping nut, and using plyers pull out the protective insert from the fitting (see Fig. 4) 

Summary of Contents for FLN10

Page 1: ...INSTALLATION MAINTENANCE MANUAL FLN10 FLN20 FLN30 FLN50 FLNMIC FLNPIR...

Page 2: ...ng Regulations If in any doubt consult a qualified electrician Please isolate mains prior to installation or maintenance Check the total load on the circuit including when this product is fitted does...

Page 3: ...supply with an outer diameter of 7 9mm and a CSA of u to 1 5mm2 The use of flat cable will cause water ingress to the fitting A drip loop should be left on th incoming cable Using the bracket as a tem...

Page 4: ...ber gasket in place see Fig 2 and pass the supply cable through the compression gland Prepare the supply cable as shown by stripping back the outer sheath and basic insulation to the correct length se...

Page 5: ...pply cable through the compression gland Prepare the supply cable as shown by stripping back the outer sheath and basic insulation to the correct length see Fig 3 Fig 3 Connect the supply cable ensuri...

Page 6: ...tection area is covered Then set the TIME and LUX controls to the desired settings PIR MICROWAVE SENSOR ACCESSORY Fig 4 Align the pins on the sensor push onto the fitting and tighten ensuring a good s...

Page 7: ...for where facilities exist This product must be disconnected from the circuit if subjected to any high voltage or insulation resistance testing Irreparable damage will occur if this instruction is no...

Page 8: ...s product should fail within its warranty period it should be returned to the place of purchase for a free of charge replacement ML Accessories does not accept responsibility for any installation cost...

Reviews: