Flooded type water cooled screw chiller (PCB Control)
76
V. Installation
Safety considerations
Access to the unit must be reserved to authorized personnel, qualified and trained in monitoring and
maintenance. The access limitation device must be installed by the customer.
After the unit has been received, when it is ready to be installed or reinstalled, and before it is started up,
it must be inspected for damage. Check that the refrigerant circuit(s) is (are) intact, especially that no
components or pipes have shifted. If in doubt, carry out a leak tightness check and verify with the
manufacturer that the circuit integrity has not been impaired. If damage is detected upon receipt,
immediately file a claim with the shipping company.
Strongly recommend employing a specialized company to unload the machine.
Safety is only guaranteed, if these instructions are carefully followed. If this is not the case, there is a risk
of material deterioration and injuries to personnel.
1.
Unit installation
1).Lifting
○
1 When transporting the unit, please make sure there is no any collision happens between the unit and
other objects.
○
2 Move the unit by placing a roller in the bottom of the unit to avoid damage.
○
3
Choose a suitable crane according to the unit’s weight
(
Buy an insurance for it if it is convenient
);
Hoist the unit according to the following chart strictly. The steel rope shall wind the lifting hook one circle
to prevent steel rope slipping and causing danger when the weight is unbalanced. Security guard circle
should be set up when hoist the unit, and also abide by the local Safety Regulations when hoist the unit.
Prohibit non-staff entering the job site or staying under the unit or the hoisting crane.
Any person is not allowed to stand below the unit when sling it.