Vacuum Dry and Leakage Checking
MLCAC-UTSM-2010-10
98
Installation
2. Vacuum Dry and Leakage Checking
1) Vacuum Dry: use vacuum pump to change the moisture (liquid) into steam (gas) in the pipe and discharge it out of the pipe to make the
pipe dry. Under one atmospheric pressure, the boiling point of water(steam temperature) is 100 . Use vacuum pump to make the
pressure in the pipe near vacuum state, the boiling point of water falls relatively. When it falls under outdoor temperature, the moisture in
the pipe will be vaporized.
N ecessary
vacuum
degree
2) Vacuum dry procedure
There are two methods of vacuum dry due to different construction environment: common vacuum dry, special vacuum dry.
. Common vacuum dry procedure
Vacuum dry (for the first time)---connect the all-purpose detector to the inlet of liquid pipe and gas pipe, and run the vacuum pump more
than two hours (the vacuum pump should be below -755mmHg)
If the pump can’t achieve below -755mmHg after pumping 2 hours, moisture or leakage point will still exist in the pipe. At this time, it
should be pumped 1 hour more.
If the pump can’t achieve -755mmHg after pumping 3 hours, please check if there are some leakage points.
Vacuum placement test: place 1 hour when it achieves -755mmHg, pass if the vacuum watch shows no rising. If it rises, it shows there’s
moisture or leakage point.
Vacuuming from liquid pipe and gas pipe at the same time.
Sketch map of common vacuum dry procedure.
Summary of Contents for MLCAC-UTSM-2010-10
Page 1: ...MIDEA LCAC 50Hz R410A DC Inverter Service Manual 2011 ...
Page 2: ......
Page 4: ......
Page 16: ...Service Space MLCAC UTSM 2010 10 12 Four way Cassette Type 3 Service Space ...
Page 22: ...Field Wiring MLCAC UTSM 2010 10 18 Four way Cassette Type 10 Field Wiring Wiring chart ...
Page 23: ...MLCAC UTSM 2010 10 Field Wiring Four way Cassette Type 19 ...
Page 32: ...The Specification of Power MLCAC UTSM 2010 10 28 Duct Type 9 The Specification of Power ...
Page 33: ...MLCAC UTSM 2010 10 Field Wiring Duct Type 29 10 Field Wiring ...
Page 34: ...Field Wiring MLCAC UTSM 2010 10 30 Duct Type Air conditioner link circuit ...
Page 37: ......
Page 40: ...Service Space MLCAC UTSM 2010 10 58 Ceiling Floor Type 3 Service Space ...
Page 47: ...MLCAC UTSM 2010 10 Field Wiring Ceiling Floor Type 65 10 Field Wiring ...
Page 48: ...Field Wiring MLCAC UTSM 2010 10 66 Ceiling Floor Type ...
Page 51: ...MLCAC UTSM 2010 10 Service Space Outdoor Units 69 2 Service Space ...
Page 54: ...Wiring Diagrams MLCAC UTSM 2010 10 72 Outdoor Units MOUB 48HDN1 R ...
Page 60: ...Troubleshooting MLCAC UTSM 2010 10 78 Outdoor Units For Duct type ...
Page 89: ...MLCAC UTSM 2010 10 Control Control 107 Part 5 Control 1 Controller 108 ...