3

EV Charging station user manual

 

 

 

 

     About

Qualification of Personnel

The electrical installation, setup and maintenance of the device may only be performed by qualified 

electricians, which have received authorization from the system operator to perform such tasks. Such 

persons must have read and understood the operating manual and must comply with the information 

therein.

Requirements of qualified electricians:
    •     knowledge of general and special safety and accident prevention guidelines;

    •     knowledge of relevant electrical guidelines (e.g., DIN VDE 0100 section 600 DIN VDE    

           0100722), as well as valid national regulations;

    •     the ability to recognize risks and avoid possible dangers.

Product Description

METRON range of charging stations (Nano(+), St) and Duo(+)) is unique for its robustness and 

durability with close to zero maintenance. It is designed to charge electric vehicles and is supplied either 

with a Type 2 socket or on cable Type 2/Type 1 plug with various charging power capabilities. Nano, 

Standard and Duo are classic heavy duty charging station with basis functions. Nano+, S and Duo+ 

are advanced charging stations with WiFi Charge Control app. and can be equipped with special Metron 

Dynamic Power Control system which protects the main household fuse and allow solar SURPLUS charging 

where the house has a solar power plant installed.
The METRON charging station is meant to be used in private and semi-public areas, such as company car 

parks, depots or private land.

The charging station is used exclusively for charging electrically powered vehicles.
    •     Mode 3 charging according to IEC 61851-1:2010.

    •     Plugs and sockets according to IEC 62196.

 

Basic features of METRON charging stations:
    •     Communication with EV through METRON Micro EVSE 1 or Micro EVSE 3 control unit

    •     Status information through LED

    •     Push button for setting charging current

    •     Durable steel casing with aluminum front panel

    •     Simplified maintenance – hinged front panel opens with a key  

    •     Modular robust design – every component can be tested and/or replaced, separately 

    •     Built-in WEB SERVER with preloaded METRON Charge Control app. & WiFi connectivity 

           (standard for “+” models)

    •     Dynamic Power Control system (optional for “+” models)

    •     RFID charging enable (optional for “+” models)

    •     MID certified Energy meter (optional for all models)

    •     Spiral cable (optional for all models)

    •     Type 2 socket with locking mechanism (optional for all models) 

    •     Type 2 plug holder – protects conductive parts of the plug from water, insects and other filth 

           (optional for all models, holder location can be per customer request)

    •     Type 2 plug with integrated Tesla remote for opening charge port and unlocking the plug 

           (optional for all models)

Summary of Contents for Duo(+)

Page 1: ...ENGLISH EV CHARGING STATION USER MANUAL...

Page 2: ...ing However because continuous improvement is a goal at Metron we reserve the right to make product modifications at any time To communicate any inaccuracies or omissions in this document please send...

Page 3: ...stacles 9 Wall installation of the charging station 10 Electrical connection 11 Supply Voltage 11 Safeguarding and personal protection 11 Connecting the supply line 12 Operation 13 Setting the chargin...

Page 4: ...idual risks associated with the device under the following circumstances the device is not used as intended non compliance with the safety information given in this manual the device is damaged the de...

Page 5: ...which protects the main household fuse and allow solar SURPLUS charging where the house has a solar power plant installed The METRON charging station is meant to be used in private and semi public are...

Page 6: ...ufacturer Type Supply voltage and charging current settings Temperature operating range Country of origin Web page Serial number Production year Certification mark Protection class 1 2 3 Charging sock...

Page 7: ...indicator Push button Socket optionally with Type 2 Type 1 plug METRON Micro EVSE 1 or Micro EVSE 3 charge controller Charge controller power supply fuse Charging fuse Residual current protection devi...

Page 8: ...age frequency range from 90 V up to 270 V 50 60 Hz from 90 V up to 270 V phase voltage 50 60 Hz from 90 V up to 270 V phase voltage 50 60 Hz Cable length if ordered with plug and cable 5m premium qual...

Page 9: ...operational and storage max 95 without condensation max 95 without condensation max 95 without condensation Storage temperature From 40 C up to 70 C From 40 C up to 70 C From 40 C up to 70 C Minimum r...

Page 10: ...irements must be met Choosing the charging station location Warning Risk due to unsuitable environmental conditions installation locations Unsuitable ambient conditions and installation locations may...

Page 11: ...acles Maintain the specified minimum distances for unrestricted access during operation maintenance and repair The dimensions are given in mm 300 300 300 300 1 2 3 4 Insert the key in the keyhole Turn...

Page 12: ...of the charging station at a height up to the top edge of the casing of approximately 1 50 meters above the finished floor Make certain that charging station has been fitted firmly and securely A Nano...

Page 13: ...onal local regulations Ensure a clockwise rotating field for a three phase connection Safeguarding and personal protection Warning Danger to life by electric shock Residual current circuit breakers ty...

Page 14: ...r conductors 3 Check that the individual cores are properly connected and that the screws are tightened 4 Turn the reset lever to position to power the system Maximum conductor circumference in the po...

Page 15: ...4 kW 3x32 A 22 kW Duo 2 x 11 kW Duo 2 x 22 kW Number of LED blinks 1 2 3 4 5 6 7 8 Charging current power 2x3x6 A 2x4 1 kW 2x3x8 A 2x5 5 kW 2x3x10 A 2x6 9 kW 2x3x13 A 2x9 0 kW 2x3x16 A 2x11 0 kW 2x3x2...

Page 16: ...tions User can set the desired charging current and delay charging start User can turn on off solar SURPLUS charging if solar power plant is installed User can see all the real time measurements of ch...

Page 17: ...name ssid is reset to default value METRON Station 1 and forgotten password is reset to default value 12345678 but it s not yet activated To activate default WiFi password and default WiFi name you n...

Page 18: ...her household appliances might draw from the in house grid There are 3 options for installing Dynamic Power Control system main fuse protection A If there is 1 charging station in the house the curren...

Page 19: ...D slowly blinks The maximum available charging current depends on the following points Power rating of the charging station Features version of the charging station Current load capacity of the chargi...

Page 20: ...you cannot fix the error or fault ask a qualified electrician to check the charging station LED status Information Slow blinking immediately after turning on the charging station Blinks indicate last...

Page 21: ...t circuit the unit Cover neighbouring components that are under voltage and secure the danger area Maintenance Plan Caution Carry out the following maintenance work at the specified intervals Maintena...

Page 22: ...of old devices must comply with the common national and regional laws and regulations Ecological considerations must be taken into account Old devices and batteries cannot be disposed of with househo...

Page 23: ...ve been used in accordance with the user manual This limited warranty does not cover Damage due to improper use Damage done by incorrect setting Accidental or intentional damage Misuse abuse corrosion...

Page 24: ......

Reviews: