Conducting Surge tests
1. Ensure that the
Active Folder
and
Active Record
are those that you want to use for the
subsequent tests, and that the
Configuration Options
icon is set to
Standalone.
Figure 22. Surge test start screen.
Basic Testing Procedures
www.megger.com
17
2. Touching the
Coil Mode Selection
icon in the
Mode Submenu
brings up the popup menu
shown below to select the mode needed. For this example, touch the
Three-phase coil mode
icon.
3. The
Lead Selection
icons default to coil No. 1 to start the test.
4. As noted earlier, the operating voltage is the basis for the test voltage used during Surge
testing. For this example, we continue to use the 480-volt motor with a maximum testing
voltage of 2000 volts.
5. Press and hold the
Start (PTT)
button. The following popup menu appears.
Figure 23. Coil Mode Selection popup menu.