Checklist

 

AGDS-MCM 

v2

 

It is essential that the installation is carried out in the order given  

below to ensure the correct operation of the system. 

 

First read the system description sheet before following the  

instructions below 

 

 
 

1. 

Connect the Control valve twin & earth to the marked terminals. 

2. 

Connect BMS, beacons, sounders etc to the relay outputs. 

3. 

Connect any additional EM stop buttons and thermal links in  series to the terminals marked “em stop” 

4. 

Each detector has a blue rotary selector switch and each switch should be  set to a different number or letter starting with 
“0”. Then connect the gas detectors to terminals marked “detectors” (

11,12

) on the panel.  Detectors can be wired “Daisy 

chain”. 

5. 

Connect the 3 amp fused spur 240 volt supply to marked  terminals (

2

). 

6. 

Once power is connected to the panel the detectors will flash the green LEDs for 90 seconds after which the LEDs will be on  
continuously. 

7. 

Press the “learn field button” this is on the main circuit board (no 

21

). Pressing this once allows the panel to learn how many 

and which type of  detectors are fitted. 

8. 

Press the “Detectors” button on the front panel and check on the display that all the detectors have been recognised by the 
system. A recognised detector will appear as “

CMOX”

,

 “CDOX”

,

 “CMBS”

 or 

“OXYG”  

with the detector reading now to it. Use 

the UP and Down buttons to page through the detector listing to check all addresses. 

Note

 that a detector set at 0 appears 

as 1 on the LCD and a detector set as 1 appears as 2 on the LCD etc. 

9. 

At this point turn the on/off switch to the on position and panel will open the gas valve.  

10. 

A functionality test of the detectors can be carried out by applying a small amount of target gas to the detectors. The 
detector LED will turn red and the panel will alarm and close the valve. 

Please do not hesitate to call for advice on the  

following numbers: 

0161 233 0600 office hours 

Or out of hours call: 07843 355163 UK only 

Notes. 

It is recommended that all systems are commissioned after installation by Medem UK. This will extend the warranty period from 5 

years to 10 years and ensure the system is working as designed.  

Please see warranty conditions that came with the main panel 

Summary of Contents for AGDS-MCM v2

Page 1: ...ilation on via a relay Before commencing installation please familiarise yourself to the equipment by reading the comprehensive installation instructions If in doubt then please call 0161 233 0600 Out...

Page 2: ...tors are set to alarm at 5 LEL pre alarm and 10 LEL for the high alarm Carbon Monoxide detectors are set to alarm at 20ppm pre alarm and 30ppm for high alarm Carbon Dioxide detectors have settable hig...

Page 3: ...0 10 volt output to fan speed controllers based on CO2 and temperature levels 15 SELV Output for low power beacons toners Set using switch 26 16 Enable Disable internal toner 17 BMS relays settings f...

Page 4: ...lways recommend using screen cable if the distance between the main panel and the detectors is greater than 20metres a 1mm screened cable must be used on the VE 0v terminals Gas detectors require a fo...

Page 5: ...ould be wired in series with the EM stop buttons To EM Stop connections in the panel Indicator bar shows when pressed Normal EM Stop Activated Multiple Stop Buttons Single Stop Buttons Resetting indic...

Page 6: ...here are five relays on the system which can be used for connecting to a BMS or sounder Beacon etc these can be set for switching to various conditions using the table below There are two mains rated...

Page 7: ...ngs Medem UK Ltd would always recommend an onsite risk assessment be carried out before any changes are implemented 28 OPT A Spare OPT B Auto restart on power failure and fire alarm off by default 2MA...

Page 8: ...gas that is being monitored for See the gas detectors own instructions for more guidance VE supply Comm s From either the main panel Address Selector Each detector must be set to its own address And...

Page 9: ...bove standing head height and between 1m and 3m from the potential source Care should be taken so they are not located close to the edge of a canopy or in direct flow of the supply or extract ventilat...

Page 10: ...plier Medem UK will exchange faulty valves for return to the manufacturer 5 Where a Medem UK engineer or another company appointed by Medem UK commission and installed system then that system will car...

Page 11: ...this once allows the panel to learn how many and which type of detectors are fitted 8 Press the Detectors button on the front panel and check on the display that all the detectors have been recognise...

Reviews: