MM710
Installation Instructions
21
20
Customer Support
1.800.897.9755 x1
36
Make Post-Leveling adjustments, if necessary.
Place a level on top of the TV while it’s in the UP position.
If it’s level, the installation is complete! If not, slightly
loosen all four Leveling Screws {15} and rotate the TV
until it’s level and then tighten all the Screws.
5.4
5.5
Adjust the Vertical Tilt Position.
Locate the two sliding knobs on each side of the Tilt
Mechanism on the Lifting Arm {35}. Slightly loosen
the knobs and position the TV to the desired tilt, then
tighten the knobs.
The tilt will remain at the same angle while the mount is
raised or lowered, unless it is manually changed.
5.6
(Steps 5.7 and 5.8 only apply if the cable box was installed
inside the area of the Wall Frame, which will require an
access hole through the Wall Cover.)
Measure carefully OR use transfer paint (similar to lipstick)
to transfer the box location onto the Wall Cover {29}.
5.7
Use 1.5 inch Hole Saw drill bit to cut a hole through the
Wall Cover {29} directly in the center of the marked area.
Be careful not to damage the edge around the hole.
5.8
5.10
Paint the Wall Covers {29} if desired.
5.9
Attach the eight Wall Cover Clips to the wall frame as
shown below. These will be used to attach the adhesive
Velcro strips that hold the wall covers to the wall frame.
Fine Tuning the Vertical Tilt Position:
The large screw inside the Lifting Mechanism can be used
fine tune the vertical straightness of the TV while in the
UP position, but it is only needed if the TV can not get
vertical using the standard tilt adjustment.
Backing this screw out a few turns will push the bottom
of the TV slightly outward..
{15} x4