3.3 OPENING THE BOX
Open the box as seen in the above sketch. Place the box on the ground, arrows on the
box pointing to the ground. Cut the cords or remove the staples, fold the lids of the box
on each side and turn the box upside down. Pull the box upwards and remove it.
3.4 INSTRUCTIONS FOR MOUNTING
Boiler should not be installed in humid places such as bathrooms and areas that may be
affected by rain water.
The boiler should be installed on strong walls that can carry it and perpendicular to the
ground.
Spesific space must be left around the for the authorized service to intervene in the
event of a technical breakdown or maintenance. You can find the minimum spaces
required for installation in the below diagram.
Only use the dowel, screw and hanger assemblies supplied with the device during
installation.It is a must to install the device vertically and smoothly with a water balance
so that it can work properly after installation.
3.5 MINIMUM SPACES FOR INSTALLATION
At least the following space must be left in order to reach the internal parts of the device
easily whe a fault occurs or when maintenance is carried out.
Suggested space is the minimum space and it is favorable to leave more space
depending on the situation.
8
Summary of Contents for Omega 6
Page 1: ...rev no 01 05 2018...
Page 6: ...2 2 COMPONENTS OF THE BOILER 5...
Page 14: ...5 TECHNICAL TABLE 13...
Page 15: ...6 ELECTRICITY CONNECTION DIAGRAM 14...
Page 19: ......