4.1 INSTALLATION AND WATER FLOOD

 

Please use open expansion tank for MAKTEK Solid Fuel Boilers. Closed expansion tank 
systems may trigger steaming of the boiler when there is an electric cut out or when the 
pump is not functioning. 

Please connect open expansion tanks according to standarts. 

No valve or similar materials must be installed on safety return or flow line of the open 

expansion tank. 

In order to increase safety if the pump does not function,a by pass line must be secured 

between inlet and outlet spot of circulation pump as show in installation schema. The valve 

on by pass line should be kept closed during normal functioning . ıf there is an electricity cut 

and a risk of overheating appears, the valve must be open and the evacuation of hot water 

must be provided by natural circulation. The diameter of the pipe to be used at by pass line 

should be the same diameter size with the pipe used in installation at minimum. 

As an extra security measure, an infinite power source may be used for electricty cut. 

Please mount 3 bar security valve on the boiler for safety against over pressure in open 

expansion systems. 

We suggest the mounting of the pump on return line in order to  protect from over heating 
(steam). 

All connections and valve positions must be checked after the installation of the boiler is 

complete. 

Operations like water flooding or evacuation must be done while the boiler is not working 
and cold. 

Please flood water to the system until water comes out of warning  pipe. Please close the 

valves when the filling is complete. 

Please purge air in the system where necessary. Avoid any installation that might block air in 

the system, if any doubt, please use automatic purger. 

 

9  

Summary of Contents for 25 MKB-S

Page 1: ...KTEK INSTALLATION USE AND MAINTAINENCE GUIDE FOR AUTOMATIC 4PASS AND DOUBLE FUEL BOILERS 25 MKB S 40 MKB S 60 MKB S 25 MKBC 40 MKBC 60 MKBC kk 07 CE TS EN ISO 9001 2015 rev na 04 Please read Please ke...

Page 2: ...ATER FLOOD BOILER INSTALLATION SCHEMA 4 2 AIR CONNECTION 4 3 CHIMNEY CHIMNEY CONNECTION SCHEMA 5 TECHICAL FEATURES 6 CONTROL PANEL 7 FIRST OPERATION AND USE 7 1 FIRST BURNING 7 2 WARNINGS FOR USE 8 CL...

Page 3: ...Turkey and World market Our company which has acquired advanced technology and superior quality stands on in accordance with these principles This handbook is a helpful guide during operation and mai...

Page 4: ...is strictly forbidden Please do not operate the boiler without water Do not feed cold water to hot boiler If for any reason the boiler temprature is over 90 C do not attempt to feed cold water to the...

Page 5: ...ndan ayarlayarak izleme imkan Opportunity for watching and setting feeding and waiting time on the electronic panel control Detritions on heating are minimised with the cast burning bunker Fan with qu...

Page 6: ...3 SECTIONS OF THE BOILER See techic table for dimensions stated with letters 6...

Page 7: ...tallations Boiler must be connected to a good drawing chimney and minimum quantity elbows should be used between chimney and boiler Boiler must be placed where has enough air for an efificient burning...

Page 8: ...water return pipe Attention should be paid to leave enough working space for service intervention boiler control and fuel feeding while installation Valve connection should be made on boiler water ent...

Page 9: ...of hot water must be provided by natural circulation The diameter of the pipe to be used at by pass line should be the same diameter size with the pipe used in installation at minimum As an extra secu...

Page 10: ...BOILER INSTALLATION SCHEMA 10...

Page 11: ...al length must not be shorter than 60 cm and longer than 2 meters and pipe must be connected to the chimney with minimum 10 degree of angle We suggest not to use enamel stove pipes as it creates tar i...

Page 12: ...e building if the chimney must pass from outside the isolation must be done properly The chimney must be frequently cleaned in order to avoid tar and soot and clogs Please avoid foreign objects cement...

Page 13: ...5 TECHNICAL SPECIFICATION 13...

Page 14: ...n setting condition setting value is shown in screen Fuel Waiting time setting button Sets the waiting period after fuel loading 04 255 sec Fuel feeding Time setting button Sets fuel loading period 04...

Page 15: ...prevents entrance of foreign materials big sized coal pieces inside the bunker and prevents damage to the reducer and loading spiral Also passes the proper size of coal which will burn easily and eff...

Page 16: ...ater decreases 5 C below set degree Running and stopping of circulation pump and fan can be followed by blinking leds on digital display on control panel Circulation pump will run automatically 3 seco...

Page 17: ...ich don t have air flow should be opened Air holes should be cleaned up by running fan free Electricity connection shoul be cut off before the maintainance Electricity chimney installation connections...

Page 18: ...10 ELECTRICITY SCHEMA 18...

Page 19: ...uel wet spilled stucked and can not be loaded Fuel is pumped down by applying pressure with an object Smoke comes from chimney connections There is H3 warning on control panel digital screen H1 warnin...

Page 20: ...e of the supporting ring When the boiler lifted up with crane there shouldn t any living being under the boiler Boiler must be carried with its accessories installed on it B CARRYING BOILER ON VEHICLE...

Page 21: ...Seller Maktek Kazan Radyator Klima San A 10013 Sk No 14 A O S B i li ZM R Tel 0 232 328 21 06 07 08 Faks 0 232 328 04 86 www maktek com tr info maktek com tr...

Reviews: