Model OE-10
Installation, Operation and Maintenance
Page
5
Rev. 4/20/07
4) Install Power Column locking pawl and lock
release clevis with 5/8” diameter x 1 1/2” lg
shoulder bolt and 1/2”-13 nylon lock nut,
Fig. 6.
Attach 3/8” O.D. extension spring to
upper hole in locking pawl and other end to
hole in bracket welded to column.
5) Attach ½” O.D. extension spring to hole
located on bottom side of Idler Column lock
pawl and install using 5/8” shoulder bolt and
lock nut,
Fig 6.
Attach 3/8” O.D. spring the
same as Power side.
A
NCHORING
6) The anchor bolts must be installed at least 8”
from any crack, edge, or expansion joint.
7) Use a concrete hammer drill with a 3/4 inch
carbide bit. Tip diameter should conform to
ANSI Standard B94.12-1977 (.775 to .787).
Do not use excessively worn bits or bits
which have been incorrectly sharpened. A
core bit may be necessary if an obstruction is
encountered.
Never substitute with shorter
anchor.
8) Recheck “Inside of Columns” dimension,
Fig 1
. Drill the anchor holes using the base
plate as a template. Drill through the floor if
possible or to a depth of 5 inches minimum.
Complete steps 8 thru 11 for the five (5)
exposed anchors around each column, then
raise the carriages. Repeat steps 8 thru 11 for
the two (2) anchors under each carriage.
9) Vacuum dust from the hole for proper holding
power.
10) Shim both columns to plumb using the shims
provided as shown in
Fig 2
. DO NOT shim
more than 1/2" at any given point. Use a level
no less than 24” in length to plumb columns.
11) Assemble washer and nut to anchor with nut
just below impact section of bolt. Drive
anchor into hole until nut and washer contact
base.
Fig 2 –
Column Shimming
12) Tighten power column anchors and recheck
column for plumb. Reshim if necessary.
Torque to 150 foot pounds to set anchors.
O
VERHEAD
13) Before raising overhead into position install 4
each (2 per column) hex flange bolts and
nuts in middle hole of column extension
(see
Fig 3 Installation Aid)
for temporary support of
overhead. Lift overhead assembly up into
position and install with 8 each (4 per
column) 3/8-16 x 3/4” lg hex flange bolts and
hex flange nuts per side as shown in
Fig 3
.
Fig 3 –
Overhead Assembly
14) Check idler column shimming. Use additional
shims (
see Fig. 2
) to remove any gaps that
may have been created while installing
overhead beam. Tighten anchor bolts and re-
check column for plumb. Torque to 150 foot
pounds.
15) Install Overhead Limit Switch to
REAR
of
Power Column using (1) 3/8” pivot pin, (1)
3/8” flat washer and (1) hairpin cotter pin as
shown below. Switch MUST pivot freely on
pin for proper function. NOTE switch tube
cord is to be oriented
above
pivot pin as
shown in
Fig 4a.
Leave switch cord hanging
at this time.
Fig 4a –
Overhead Limit Switch Sub-Assembly
A2151_MAGNUM.doc