4.1 Foundation frame
The foundation frame is required for turnstiles to be mounted on an uneven
surface, for example in case of pavers. A level concrete mounting surface is
required for correct mounting of the foundation frame. It should be approx.
150 mm below the finished surface.
The foundation frame must be positioned in its desired location taking care on
which side (right or left), you want to place part 2. This is important in case
you want to mount access control units at part 2.
(See Fig 2.1 / 2.2, Fig. 5.1 / 5.2, Fig. 6)
Installation of the foundation frame:
First of all put the frame in place
Drill the fixing holes
Insert the fixing screws
Install the foundation frame by means of jackscrews in water
(if needed, even out with suitable underlayment)
Then fix the foundation frame
Pay attention to correct cable guiding to the turnstile
Empty conduits must not be squeezed
Please consider the cure time of the chemical anchor studs
With the installed foundation frame, the mounting of the turnstile can be
carried out in the same way as on a concrete foundation. (See chap. 5)
5
Fundamentdübel(F)
Express-Anker M12x153/55 A4
Bohrloch
Ǿ
12
Bohrtiefe 145 mm incl. U-Profilhöhe
Cable routing from foundation
into turnstile
Jackscrews
For positioning the foundation
frame on the concrete, if necessary.
Fig.5
Fig. 5.1 Entry Left version
Fig. 5.2 Entry Right version