I422 GB I 10 17
31100212
G
B
10
Code
COMMAND
ACCESS LEVEL
DESCRIPTION
C.01
RESET HI-LO
User / Advanced
Resets the HI and LO values of all measurements
C.02
RESET MAX DEMAND
User / Advanced
Resets Max Demand values for all measurements
C.03
RESET PARTIAL ENERGY METERS
User / Advanced
Resets partial energy meters
C.04
RESET PARTIAL HOUR COUNTER
User / Advanced
Resets partial hour counters
C.07
RESET ALARMS
User / Advanced
Resets alarms with latch
C.08
RESET LIMITS
User / Advanced
Resets limit thresholds with latch
C.11
RESET TOTAL ENERGY METER
Advanced
Resets total and partial energy meters
C.12
RESET TOTAL HOUR COUNTERS
Advanced
Resets total hour counters
C.13
PARAMETERS TO DEFAULT
Advanced
Restores all settings to factory default values
C.14
PARAMETER BACKUP
Advanced
Saves a backup copy of the settings
C.15
PARAMETERS RESTORE
Advanced
Reloads the settings from the backup copy
C.16
WIRING TEST
Advanced
Runs the test to check that the DMG is connected correctly.
See Connection Test section
COMMANDS MENU
– The commands menu permits the execution of occasional operations such as resetting measurements, meters, counter, etc.
– If the advanced-access password has been entered, the commands menu can also be used to perform some automatic operations that are useful for configuring the instrument.
– The following table indicates the functions available through the commands menu, divided by required access level.
– Once the desired command is selected, press
to execute it. The instrument will request confirmation. Pressing
again will execute the command.
– To cancel the execution of a selected command, press
MENU
.
– To abandon the command menu, press
MENU
.
CONNECTION TEST
– The connection test permits verification of the correct installation of the multimeter.
– In order to run the test, the multimeter must be connected to an active system with the following conditions:
• three-phase system with all phases present (V > 50VAC PH-N)
• minimum current flow in each phase > 1% of the CT full scale set
• positive flow of energies (i.e. a normal system where the inductive load draws power from the supply)
– To launch the test, enter the commands menu and select command C.16, according to the instructions in the Commands Menu section.
– The test permits verification of the following:
• reading of the three voltages
• phase sequence
• voltage unbalance
• reverse polarity of one or more CTs
• mismatch between voltage/current phases
– If the test is not passed, the display shows the reason for the failure.