10/30
1.3.6
During all movements, operating personnel must ensure that they and other people are not
endangered. All obstacles which may hinder the operation or implementation of the machine at the
location of use must be moved out of the way.
1.3.7
Work on the electrical equipment of the machine may only be carried out by qualified electricians or
trained personnel under the management and supervision of a qualified electrician, and in
accordance with the rules of electronics.
1.3.8
Any personnel training, learning, being instructed, or currently involved in general education may
only work with the machine under the continual supervision of an experienced person!
1.4.
Safety instructions for operation phases
1.4.1.
Transport, assembly and installation
1.4.1.1
Transport, assembly and installation may only be carried out in transport position. Secure the
waste water suction against rolling away.
1.4.1.2
Transport should be done exclusively via crane and considering the maximum operating weight in
terms of lifting and lowering. It can be moved manually over level floors.
1.4.1.3
Transport may only be done, as long as all machine parts are tightened on the machine and
individual parts cannot fall.
1.4.2.
Commissioning
1.4.2.1
The commissioning may only be carried out in transport position. Parking brake must be active.
1.4.2.2
All obstacles must be cleared away from the working area and also make sure there is sufficient
lighting.
1.4.2.3 Visual
inspection for damages and defects. Special check of the safety equipment and the water
hoses.
1.4.2.4
Smoking is absolutely prohibited when filling the fuel motor.
1.4.2.5
Special care must be taken when refilling the fuel tank. Motor parts that become warm during
operating become a fire hazard.
1.4.2.6
Fuel storage may only be in authorized containers.
1.4.2.7
Mount the exhaust hose or floor nozzle on the waste water suction.