This tab is used to test the VRI system. Only Certified Lindsay Dealers are allowed to operate the Test Screen.
The following functions can be performed in the Test Tab:
Enable Pulse Mode
Selecting the “Enable Pulse Mode” check-box will pulse the VRI irrigation plan. If this box is not checked while
pulsing the valves; after 3 to 5 minutes of pulsing, the VRI Main Controller will return back to the VRI irrigation
plan.
NOTE: The Plan cannot be changed while Pulse Mode is enabled.
Force Valve Open 100%
Pressing this button will force all nodes to open the valves (100% application rate).
I/O Testing
The I/O test display allows the Technician to manually test the Inputs and Outputs of the VRI System.
WARNING:
Pulsing the valves at a high rate can cause the pivot, and especially the overhang, to
shake violently and possibly damage the system. Starting with a Forced Period of ten seconds or
higher and rate of 50% can reduce this effect.
This initial test setting may need a higher Forced Period with a rate lower than 50% on smaller model/
designed pivots.
Summary of Contents for GROWSMART
Page 1: ...Variable Rate Irrigation Installation Manual P N 1600043 Rev M ECN 34095...
Page 2: ......
Page 4: ...P N 1600043 Rev M ECN 34095 VRI Installation Manual...
Page 27: ...P N 1600043 Rev M ECN 34095 13 VRI Installation Manual This page is left blank intentionally...
Page 30: ...P N 1600043 Rev M ECN 34095 16 VRI Installation Manual VRI VISION BOSS Control Panel Wiring...
Page 44: ...P N 1600043 Rev M ECN 34095 30 VRI Installation Manual...
Page 52: ...P N 1600043 Rev M ECN 34095 APDX 8 VRI Installation Manual Appendix...
Page 54: ...P N 1600043 VRI Operation Installation Manual Revisions...