TROUBLESHOOTING / GAS OVENS 1033, 1034, 1046, 1047
SYMPTOM
POSSIBLE CAUSE
EVALUATION
Incoming Power Supply
Check breaker/reset if required. Call Power
Company if needed. In these ovens, there is a
control circuit step-down transformer. This
transformer steps down supply voltage to 120 VAC.
If main fan will not run, the secondary of this
transformer must be checked for 120 VAC output.
Check specific oven model schematic for circuit
location.
Transformer Fuse
Check and/or replace.
Fuseholder
Check and/or replace.
Fan Switch
Check continuity between switch terminals.
Oven Start Relay
Check for 120 VAC to the relay coil. If voltage is not
present, trace wiring back to the fan switch. If
voltage is present, check to insure contacts are
closing.
20 Minute Time Delay
Check for 120 VAC at terminal #1 to neutral on the
20-minute timer. If no voltage is present, trace
wiring back to the power supply. If voltage is
present at terminal #1, check for 120 VAC at
terminal #2 to neutral. If no voltage is present, and
the oven start relay is closed, replace the 20-
minute timer.
Oven Fan Relay
Check for 120 VAC to coil of the oven fan relay. If
no voltage is present, trace wiring back to terminal
#2 of the 20-minute timer. Check for 120 VAC at
terminals #2 and 6 of the relay, if no voltage is
present, trace wiring back to the power supply. If
voltage is present at the relay coil, check to insure
the contacts are closing.
Fan Fuse
Check, replace if necessary.
Fuseholder
Check, replace if necessary.
Capacitor
Check for opens, shorts, or grounds.
Oven fan will not run
Motor
Check for opens, shorts, or grounds. WITH
POWER OFF: turn the fan blade to check for
locked rotor.
20 Minute Time Delay
Check for 120 VAC at terminal #2 to neutral while
oven is "on". Turn off the main fan switch, 120 VAC
should continue to be present for 20 minutes. If
voltage is not present for approx. 20 minutes,
replace the timer.
No main fan cool down
Oven Fan Relay
Check if relay is operating and that the contacts
remain closed during the 20 minute cool down.
Oven Start Relay
Contacts should open when main fan switch is
turned off.
20 Minute Time Delay
120 VAC at terminal #2 should discontinue
approximately 20 minutes after main fan is
switched off. If the oven start relay contacts are
open, and the voltage continues at terminal #2 of
the 20 minute timer, replace the timer.
Main fan runs after 20
minute cool down
Oven Fan Relay
Check to insure that the contacts are opening after
the coil is de-energized.
No control box cooling Fan Switch Oven Start
Relay20 Minute Time Delay
Oven Fan Relay Cooling
Fans
(SEE MAIN FAN WILL NOT RUN) 120 VAC should
now be at this motor. If voltage is present, check
motor for shorts, opens, or grounds. WITH POWER
OFF: check for locked rotor.
Summary of Contents for Impinger 1002
Page 12: ...Impinger I 1000 Series Service Manual International 12 SCHEMATIC 1002 1003...
Page 13: ...Impinger I 1000 Series Service Manual International 13 SCHEMATIC 1006 TO SERIAL NUMBERS Q14279...
Page 14: ...Impinger I 1000 Series Service Manual International 14 SCHEMATIC 1028 1029 S N Q19071 BELOW...
Page 15: ...Impinger I 1000 Series Service Manual International 15 SCHEMATIC 1028 1029 S N Q19078 ABOVE...
Page 16: ...Impinger I 1000 Series Service Manual International 16 SCHEMATIC 1030 TO S N Q17170...
Page 17: ...Impinger I 1000 Series Service Manual International 17 SCHEMATIC 1030 S N Q17171 ABOVE...
Page 18: ...Impinger I 1000 Series Service Manual International 18 SCHEMATIC 1032 S N Q19077 BELOW...
Page 19: ...Impinger I 1000 Series Service Manual International 19 SCHEMATIC 1032 S N Q19078 ABOVE...
Page 20: ...Impinger I 1000 Series Service Manual International 20 SCHEMATIC 1033 1034 1046 1047...
Page 21: ...Impinger I 1000 Series Service Manual International 21 SCHEMATIC 1042 1043 S N Q14279 BELOW...
Page 22: ...Impinger I 1000 Series Service Manual International 22 SCHEMATIC 1042 1043 S N Q14280 ABOVE...
Page 23: ...Impinger I 1000 Series Service Manual International 23 SCHEMATIC 1228 1229 S N Q14790 BELOW...
Page 24: ...Impinger I 1000 Series Service Manual International 24 SCHEMATIC 1228 1229 S N Q14791 ABOVE...
Page 25: ...Impinger I 1000 Series Service Manual International 25 SCHEMATIC 1242 1243...
Page 81: ...Impinger I 1000 Series Service Manual International 81 BLOW UP 1000 1200 GENERAL...
Page 83: ...Impinger I 1000 Series Service Manual International 83 BLOW UP 1002 1003 S N 2584 TO 4389...
Page 85: ...Impinger I 1000 Series Service Manual International 85 BLOW UP 1002 1003 S N 4390 ABOVE...
Page 87: ...Impinger I 1000 Series Service Manual International 87 BLOW UP 1006...
Page 89: ...Impinger I 1000 Series Service Manual International 89 BLOW UP 1028 1029 1032...
Page 91: ...Impinger I 1000 Series Service Manual International 91 BLOW UP 1030...
Page 93: ...Impinger I 1000 Series Service Manual International 93 BLOW UP 1042 1043...
Page 95: ...Impinger I 1000 Series Service Manual International 95 BLOW UP 1033 1034 1046 1047...
Page 97: ...Impinger I 1000 Series Service Manual International 97 BLOW UP 1228 1229...
Page 99: ...Impinger I 1000 Series Service Manual International 99 BLOW UP 1242 1243...
Page 101: ...Impinger I 1000 Series Service Manual International 101 BLOW UP OVEN BACK GAS...
Page 103: ...Impinger I 1000 Series Service Manual International 103 BLOW UP OVEN BACK ELECTRIC...
Page 107: ...Impinger I 1000 Series Service Manual International 107 BLOW UP SERIES 1000 CONVEYOR...
Page 109: ...Impinger I 1000 Series Service Manual International 109 BLOW UP SERIES 1200 CONVEYOR CONTROL...
Page 111: ...Impinger I 1000 Series Service Manual International 111 BLOW UP SERIES 1200 CONVEYOR...
Page 112: ...Impinger I 1000 Series Service Manual International 112...