Chapter 2 - Installation
UPStation GXT 3x1
Page 6
(06/02)
2.4.4
Stabilisers/Levelling feet
When the UPS is located in its final position before or after wiring, it is necessary to fit stabiliser brackets and, if
necessary, adjust the levelling feet. If the UPS is wired using a rigid wiring system, then movement of the UPS must be
prevented by winding down the 4 levelling feet under the UPS as shown below. For UPS wired with flexible cables, this
is optional.
Note
: - Access to the levelling feet is obstructed by the stabiliser brackets, on the GXT 3x1 - 6000/8000/10000 models.
Adjust the levelling feet as necessary using a 12mm open ended spanner/wrench. DO NOT LOOSEN THE LARGER
NUT ABOVE, AS THIS FIXES THE LEVELLING FEET TO THE CHASSIS.
Attach the stabilising brackets as follows.
GXT3x1-6000, GXT3x1-8000, GXT3x1-10000 models:
1
Using a Phillips-head screwdriver, remove the three inner-most screws at the base of both side panels.
2
Attach the stabilisers fixing with the screws just removed.
Figure 2-2
Levelling Feet Adjustment Diagram
12 mm