Maintenance Manual of Elevating Work Platform
14
This check shall be made once per 25h or per
month, whichever is shorter.
1) The normal driving function is essential to
the operation safety. With the driving
function, a rapid and stable response shall
be given to the operator. No delay, vibration
and abnormal sound shall be outputted
during the normal operation and driving
process.
2) Be sure to complete the driving test on a
firm and level ground without any barrier.
①
Draw two lines, spaced by 10m on the
ground, as the starting line and the
finishing line.
②
Switch the key switch to the platform
controller and draw out the red
emergency stop buttons from the ground
and platform controller
③
Lower the platform to the folding
position.
④
Press the drive function selector button.
⑤
Select one point from the machine as
the visual inspection reference for the
starting line and the finishing line.
⑥
Drive the machine at the maximum
speed and start to count when the
reference point passes the starting line.
⑦
Keep driving at the full speed and record
the time when the reference point
passes the finishing line. Refer to the
specification.
B-9
Test of driving speed-lifting status
This check shall be made once per 25h or per
month, whichever is shorter.
1) The normal driving function is essential to the
operation safety. With the driving function, a
rapid and stable response shall be given to
the operator. No delay, vibration and
abnormal sound shall be outputted during the
normal operation and driving process.
2) Be sure to complete the driving speed test on
a solid and level ground without any barrier.
①
Draw two lines, spaced by 10m on the
ground, as the starting line and the
finishing line.
②
Switch the key switch to the platform
controller and draw out the red emergency
stop buttons from the ground and platform
controller.
③
Press the lifting function selector button.
④
Press the enable key
⑤
Lift the platform for a given height above
the ground. The lifting height of every
model is given in the following table.
Model
Height (m)
SS0407E
1.36
AS0607E
1.19
AS0812E
1.71
AS1012E
AS1212E
1.86
AS1413E
2.52
Summary of Contents for AS0607E
Page 6: ...Maintenance Manual of Elevating Work Platform 1 Chapter 1 Maintenance...
Page 7: ...Maintenance Manual of Elevating Work Platform 2...
Page 33: ...Maintenance Manual of Elevating Work Platform 28...
Page 34: ...Maintenance Manual of Elevating Work Platform 29 Chapter 2 Appendix...
Page 35: ...Maintenance Manual of Elevating Work Platform 30...
Page 36: ...Maintenance Manual of Elevating Work Platform 31 2 1Battery Maintenance Schedule...
Page 41: ...Maintenance Manual of Elevating Work Platform 36 SS0407E SS0507E HYDRAULIC SCHEMATIC...
Page 42: ...Maintenance Manual of Elevating Work Platform 37 AS0607E HYDRAULIC SCHEMATIC...
Page 43: ...Maintenance Manual of Elevating Work Platform 38 AS0812E HYDRAULIC SCHEMATIC...
Page 44: ...Maintenance Manual of Elevating Work Platform 39 AS1012E AS1212E HYDRAULIC SCHEMATIC...
Page 45: ...Maintenance Manual of Elevating Work Platform 40 AS1413E HYDRAULIC SCHEMATIC...
Page 46: ...Maintenance Manual of Elevating Work Platform 41 SS07E ELECTRIC SCHEMATIC...
Page 47: ...Maintenance Manual of Elevating Work Platform 42 AS07E AS08E AS12E ELECTRIC SCHEMATIC...
Page 48: ...Maintenance Manual of Elevating Work Platform 43 AS1413E ELECTRIC SCHEMATIC...