
6 | INTRODUCTION
INTRODUCTION | 7
Introduction
MUL
TI V W
ater V W
ater Source Unit Engineering Manual
© LG Electronics Canada, Inc., North York, ON Canada. All rights reserved. “LG” is a registered trademark of LG Corp.
© LG Electronics Canada, Inc., North York, ON Canada. All rights reserved. “LG” is a registered trademark of LG Corp.
LATS Generates a Complete Project Report
LATS software also generates a report containing project design parameters, cooling and heating design data, system component perfor-
mance, and capacity data. The report includes system combination ratio and refrigerant charge calculations; and provides detailed bill of
material, including outdoor units, indoor units, control devices, accessories, refrigerant pipe sizes segregated by building, by system, by pipe
size, and by pipe segments. LATS can generate an Excel GERP report that can imported into the LG SOPS pricing and ordering system.
Proper Design to Install Procedure
LG encourages a two report design-to-install-procedure. After the design engineer determines building / zone loads and other details, the
engineer opens the LATS program and inputs the project’s information. When the design is complete, the “Auto Piping” and “System Check”
functions must be used to verify piping sizes, limitations, and if any design errors are present. If errors are found, engineers must adjust the
design, and run Auto Piping and System Check again. When the design passes the checks, then the engineer prints out a project “Shop
Drawing” (LATS Tree Diagram) and provides it to the installing contractor. The contractor must follow the LATS Tree Diagram when building
the piping system, but oftentimes the design changes on the building site:
• Architect has changed location and/or purpose of room(s).
• Outdoor unit cannot be placed where originally intended.
• Structural elements prevent routing the piping as planned.
• Air conditioning system conflicts with other building systems (plumbing, gas lines, etc.).
The contractor must mark any deviation from the design on the Shop Drawing, including as-built straight lines and elbows. This “Mark Up”
drawing must be returned to the design engineer or Rep, who must input contractor changes into the LATS file. (Copy the original LATS soft-
ware file, save and rename as a separate file, and modify all piping lengths by double-clicking on each length and editing information.) Like
the shop drawing, the Auto Piping and System Check must also be run on this new “As Built” drawing. The design engineer or Rep must then
provide the final As Built file to the contractor. The Mark Up version must be compared to the As Built version for:
• Differences in pipe diameter(s). If incorrect diameters have been installed, the piping must be changed out. If pipe diameters have changed,
check to see if Y-Branches will also need to be changed.
• Changes to outdoor unit and indoor unit capacities. Capacities changes may impact line length changes.
• Additional refrigerant charge quantity (“Trim Charge”). Trim charge will change if piping lengths and diameters change. The As Built version
must reflect installed piping lengths to ensure correct trim charge.
All documents submitted by the contractor, as well as the Shop Drawing and the As Built Drawing files must be provided for commissioning
purposes. Model and serial numbers for all system components must also be submitted. If the steps previously detailed are not followed,
and all documents are not provided to the commissioning agent, the project runs the risk of not being commissioned and voiding any limited
warranty LG offers on the equipment.
LG AIR CONDITIONER
TECHNICAL SOLUTION (LATS)
System R410A Refrigerant Charge Calculator (lbs.)
REFRIGERANT CHARGE WORKSHEET
1
CF (Ref.) = Correction Factor for Refrigerant Charge.
2
For refrigerant charge purposes, consider only the liquid line; ignore the vapor line(s).
System Tag or ID:
Job Name: __________________________________________
Project Manager: ____________________________________ Date: ______________
Line #
Description
Chassis I.D.
Size
Quantity CF (Ref.)
1
Total (lbs.)
1
Linear feet of 1/4" liquid line tubing
2
—
—
0.015
2
Linear feet of 3/8" liquid line tubing
2
—
—
0.041
3
Linear feet of 1/2" liquid line tubing
2
—
—
0.079
4
Linear feet of 5/8" liquid line tubing
2
—
—
0.116
5
Linear feet of 3/4" liquid line tubing
2
—
—
0.179
6
Linear feet of 7/8" liquid line tubing
2
—
—
0.238
7
Linear feet of 1" liquid line tubing
2
—
—
0.323
8
St Art Cool Mirror
SJ, SK
5k to 15k
0.53
9
St Art Cool Mirror
SJ, SK
18k to 24k
0.62
10 Standard
SV
30k to 36k
1.01
11 Art Cool Gallery
SF
9k to 12k
0.22
12 1-Way Cassette
TU
7k to 12k
0.44
13 1-Way Cassette
TT
18k to 24k
0.64
14 2-Way Cassette
TS
18k to 24k
0.75
15 4-Way 2' x 2' Cassette
TR
5k to 7k
0.40
16 4-Way 2' x 2' Cassette
TR
9k to 12k
0.55
17 4-Way 2' x 2' Cassette
TQ
15k to 18k
0.71
18 4-Way 3' x 3' Cassette
TN
7k to 24k
0.88
19 4-Way 3' x 3' Cassette
TM
28k to 36k
1.08
20 4-Way 3’ x 3’ Cassette
TM
42k to 48k
1.41
21 High Static Ducted
M1
7k to 24k
0.57
22 High Static Ducted
M2
7k to 24k
0.77
23 High Static Ducted
M2
28k to 42k
1.15
24 High Static Ducted
M3
28k to 54k
1.35
25 High Static Ducted
B8
36k to 96k
2.20
26 Low Static Ducted, Low Static Ducted Bottom Return
L1
5k to 9k
0.31
27 Low Static Ducted, Low Static Ducted Bottom Return
L2
12k to 18k
0.42
28 Low Static Ducted, Low Static Ducted Bottom Return
L3
21k to 24k
0.55
29 Vertical / Horizontal Air Handling Unit
NJ
12k to 30k
1.04
30 Vertical / Horizontal Air Handling Unit
NJ
36k
1.57
31 Vertical / Horizontal Air Handling Unit
NK
42k to 54k
2.00
32 Floor Standing
CE (U)
7k to 15k
0.37
33 Floor Standing
CF (U)
18k to 24k
0.82
34 HRU: PRHR022A/023A, 032A/033A, 042A/043A, 063A, 083A
—
—
1.1
35
TOTAL SYSTEM CHARGE
Figure 2: Example of LATS Tree Diagram