LG Multi V Water V ARWM072CAS5 Engineering Manual Download Page 34

62 |   LIMITS / PLACEMENT

LIMITS / PLACEMENT   |   63

Piping Limitations and Placement Considerations

MUL

TI V W

ater IV Source Unit Engineering Manual

© LG Electronics Canada, Inc., North York, ON Canada. All rights reserved. “LG” is a registered trademark of LG Corp.

.

© LG Electronics Canada, Inc., North York, ON Canada. All rights reserved. “LG” is a registered trademark of LG Corp.

Table 34:  Heat Pump Triple-Frame Connection Pipe Sizes.

Conditional Applications

Conditional applications are computed in LATS. See below for an explanation of when pipes are upsized.

If the equivalent length between the first Y-branch to the farthest indoor unit is >131 feet (up to 295 feet maximum): 

• Pipe segment diameters between the first Y-branch and the second Y-branch must be sized up by one. This applies to both liquid and vapor 

pipes. If the next size up is not available, or if the piping segment diameters are the same as main pipe (A) diameters, sizing up is not 

possible.

• While calculating the entire refrigerant pipe length, pipe lengths for ΣB must be multiplied by two: A+(ΣBx2)+ΣC ≤1,640 feet.

• Length of pipe (C) from each indoor unit to the closest Y-branch or header ≤ 131 ft.

• [Length of pipe from water source unit to farthest indoor unit (A+B+C)] - [Length of pipe from water source unit to closest indoor unit 

(A+B+C)] ≤131 feet.

If the pipe (B) diameters after the first branch are bigger than the main pipe (A) diameters, pipe (B) must be changed to match main pipe (A) 

sizes. 

Example: When an indoor unit combination ratio of 120% is connected to a 24-ton water source unit: 

Water source unit main pipe (A) diameters: 1-3/8 inches (vapor) and 5/8 inches (liquid).
1.  Pipe (B) diameters: 1-3/8 (vapor) and 3/4 (liquid) (after the first branch, when indoor unit combination ratio is 120% [26 tons]).

2.  After the first branch, pipe (B) diameters must be changed to 1-3/8 inches (vapor) and 5/8 inches (liquid) to match main pipe (A) sizes.

Instead of using the total indoor unit capacity to choose main pipe (A) diameters, use water source unit capacity to choose downstream main pipe 

(A) diameters. 

Do not permit connection pipes (B) from branch to branch to exceed main pipe (A) diameters as indicated by water source unit. 

capacity. Example: When an indoor unit combination ratio of 120% is connected to a 20-ton water source unit (24 tons), and indoor unit with 

a 7,000 Btu/h capacity is located at the first branch:

1. Main pipe (A) diameters on a 20-ton water source unit: 1-1/8 inches (vapor) and 5/8 inches (liquid).

2. Pipe diameters between first and second branches, however, are: 1-3/8 (vapor) and 3/4 (liquid) (connected downstream indoor unit  

capacity is 20 tons).

3. If main pipe (A) diameters of a 20-ton water source unit are 1-1/8 (vapor) and 5/8 (liquid), then the pipe diameters between the first  

and second branches must be changed to match.

PIPING LIMITATIONS

For Systems Designed for Heat Pump Configuration

Following pages present Multi V Water V piping limitations and are for illustrative purposes only. Designers MUST use LATS when designing LG VRF 

systems.

 Heat Pump Outdoor Unit Service Port Detail

PIPING LIMITATIONS

For Systems Designed for Heat Recovery Configuration

Following pages present Multi V Water V piping limitations and are for illustrative purposes only. Designers MUST use LATS when designing LG VRF 

systems.

Figure 27:  Typical Heat Recovery System Building Layout with Piping Limitations.

E lev ation

Differential

WS U to 

IDU: 164'

M ax imum Total Piping L ength: 1, 640'

E lev ation

Differential

IDU to IDU on

same H RU: 49'

E lev ation 

Differential

IDU to IDU: 131'

E lev ation

Differential 

H RU to 

H RU: 98'

L ongest pipe length: 656'  actual ( 738'  eq uiv )

For Heat Recovery Unit information, refer to the applicable Engineering Manual on 

www.lghvac.com

4

Tools

Verify the tools listed below are available for use at the installation site:

Piping

Multi V Water 5 Piping and Service Ports

LG Multi V Water 5 systems can be configured to operate as either

a heat pump or a heat recovery system. The piping MUST be

installed to the correct outdoor unit service ports according to

project specifications or the system will not operate properly. See

below for the piping installation differences between heat pump and

heat recovery systems.

Heat Pump Outdoor Unit Service Port Detail

1. Liquid piping service port (back

seated type with right hand thread).

2. Service port NOT used for heat

pump systems. Keep closed and

capped.

3. Vapor piping service port (back

seated type with right hand thread). 

4. Stem head access with factory-

provided cap.

5. Schrader ports with factory-

provided cap.

6. Service port piping to connect to

field piping.

Heat Recovery Outdoor Unit Service Port Detail

1. Liquid piping service port (back

seated type with right hand thread).

2. Low pressure vapor piping service

port (back seated type with right

hand thread).

3. Vapor piping service port (back

seated type with right hand thread). 

4. Stem head access with factory-

provided cap.

5. Schrader ports with factory-provided

cap.

6. Service port piping to connect to

field piping.

Piping Selection

ACR-rated, seamless phosphorous deoxidized copper (UNS

C12200 DHP class) is the only approved refrigerant pipe material

for LG Multi V products. Approved piping will be marked “R-410A

rated” along the length of the tube.

• Drawn temper (rigid) ACR copper tubing is available in sizes 3/8

through 2-1/8 inches (ASTM B 280, clean, dry and capped).

• Annealed temper (soft) ACR copper tubing is available in sizes

1/4 through 2-1/8 inches (ASTM B 280, clean, dry, and capped).

Handling the Piping

To avoid operation failure, a VRF system CANNOT have

contaminants or moisture in the piping network. Piping must be

kept clean, dry, and air tight. Commercially available piping,

however, often contains dust and other materials. Clean it with a

dry inert gas, and keep it capped until ready for installation. While

installing, prevent dust, water, or other contaminants from entering

the piping. When cutting the piping, hold it so copper shavings do

not fall into it, and properly remove all burrs with a de-burring tool.

Ream all piping to its full inside diameter; correctly reamed piping

will provide an excellent surface for a tight seal.

When bending piping, try to keep the number of bends to a

minimum, and use the largest radius possible to reduce the

equivalent length of installed pipe. If an obstacle is in the path of

the planned refrigerant pipe run, it is preferable to route the pipe

over the obstacle, with the length of the horizontal section of pipe

above or below the obstacle be a minimum of three (3) times the

longest vertical rise (or fall) at either end of the segment.

Piping Expansion

Expansion and contraction must be allowed in the design to avoid

fitting and piping fatigue failures. A vapor line in a Multi V water

system can change from 50° to 170° when switching from cooling

to heating. This can cause up to 1-3/8 inches expansion /

contraction per 100 feet of pipe, or about 0.001 inch / °F per 10 feet

of pipe. When a segment of pipe is mounted between 2 fixed

points, provisions must be provided to allow pipe expansion to

naturally occur, generally by expansion Loops or U-bends.

Flaring the Piping

When flaring the piping, use a dedicated R-410A flaring tool; use

only synthetic oil between the nut and the flare (not inside the

piping) to achieve correct torque and prevent leaks. Flares must be

deeper to handle the higher pressures of R-410A.

When brazing the piping, always use 15%

silver braze and a nitrogen purge. Similar to

piping medical gas, flow the nitrogen

through the piping at 1 to 3 psig to prevent

oxidation.

• Screw Drivers 

(JIS for terminal screws,  Flat, Phillips)

• Pliers

• Wire Strippers, Cutters, and Crimpers

• Hammer

• Adjustable Wrenches

• Drill and Bits

• Hole Saw

• Utility Knife

• Drop Cloth

• Pipe Cutter / Reamer

• Acetylene Brazing Outfit

• Brazing Material —15 % silver only

• Digital Multimeter and Amp Clamp

• R-410A Flaring Tool

• Torque Wrench Set

• Dedicated R-410A Refrigerant Manifold Gauge

• Dedicated 5/16" Premium Hoses

• Nitrogen regulator (for 550# test)

• 1/4" to 5/16" Hose Adapters (if needed)

• Nitrogen Tank

• Electronic Leak Detector

• 5/16" Schrader Core Removal Tool

• Vacuum Micron Gauge

• Good Quality Digital Charging Scale

• Vacuum Pump and Fresh Oil

• Refrigerant Recovery Unit and Tank

• Wall thickness must meet local code requirements and be

approved for a maximum operating pressure of 551 psi.

• LG recommends soft copper use to be limited to 1/2 inches.

Use hard drawn for larger sizes to avoid sags and kinks that

lead to oil trapping.

NOTE

!

Proper R-410A Flare.

Heat Recovery Outdoor Unit Service Port Diagram.

Heat Pump Outdoor Unit Service Port Diagram.

1

2

3

6

5

4

1

2

3

6

5

4

4

Tools

Verify the tools listed below are available for use at the installation site:

Piping

Multi V Water 5 Piping and Service Ports

LG Multi V Water 5 systems can be configured to operate as either

a heat pump or a heat recovery system. The piping MUST be

installed to the correct outdoor unit service ports according to

project specifications or the system will not operate properly. See

below for the piping installation differences between heat pump and

heat recovery systems.

Heat Pump Outdoor Unit Service Port Detail

1. Liquid piping service port (back

seated type with right hand thread).

2. Service port NOT used for heat

pump systems. Keep closed and

capped.

3. Vapor piping service port (back

seated type with right hand thread). 

4. Stem head access with factory-

provided cap.

5. Schrader ports with factory-

provided cap.

6. Service port piping to connect to

field piping.

Heat Recovery Outdoor Unit Service Port Detail

1. Liquid piping service port (back

seated type with right hand thread).

2. Low pressure vapor piping service

port (back seated type with right

hand thread).

3. Vapor piping service port (back

seated type with right hand thread). 

4. Stem head access with factory-

provided cap.

5. Schrader ports with factory-provided

cap.

6. Service port piping to connect to

field piping.

Piping Selection

ACR-rated, seamless phosphorous deoxidized copper (UNS

C12200 DHP class) is the only approved refrigerant pipe material

for LG Multi V products. Approved piping will be marked “R-410A

rated” along the length of the tube.

• Drawn temper (rigid) ACR copper tubing is available in sizes 3/8

through 2-1/8 inches (ASTM B 280, clean, dry and capped).

• Annealed temper (soft) ACR copper tubing is available in sizes

1/4 through 2-1/8 inches (ASTM B 280, clean, dry, and capped).

Handling the Piping

To avoid operation failure, a VRF system CANNOT have

contaminants or moisture in the piping network. Piping must be

kept clean, dry, and air tight. Commercially available piping,

however, often contains dust and other materials. Clean it with a

dry inert gas, and keep it capped until ready for installation. While

installing, prevent dust, water, or other contaminants from entering

the piping. When cutting the piping, hold it so copper shavings do

not fall into it, and properly remove all burrs with a de-burring tool.

Ream all piping to its full inside diameter; correctly reamed piping

will provide an excellent surface for a tight seal.

When bending piping, try to keep the number of bends to a

minimum, and use the largest radius possible to reduce the

equivalent length of installed pipe. If an obstacle is in the path of

the planned refrigerant pipe run, it is preferable to route the pipe

over the obstacle, with the length of the horizontal section of pipe

above or below the obstacle be a minimum of three (3) times the

longest vertical rise (or fall) at either end of the segment.

Piping Expansion

Expansion and contraction must be allowed in the design to avoid

fitting and piping fatigue failures. A vapor line in a Multi V water

system can change from 50° to 170° when switching from cooling

to heating. This can cause up to 1-3/8 inches expansion /

contraction per 100 feet of pipe, or about 0.001 inch / °F per 10 feet

of pipe. When a segment of pipe is mounted between 2 fixed

points, provisions must be provided to allow pipe expansion to

naturally occur, generally by expansion Loops or U-bends.

Flaring the Piping

When flaring the piping, use a dedicated R-410A flaring tool; use

only synthetic oil between the nut and the flare (not inside the

piping) to achieve correct torque and prevent leaks. Flares must be

deeper to handle the higher pressures of R-410A.

When brazing the piping, always use 15%

silver braze and a nitrogen purge. Similar to

piping medical gas, flow the nitrogen

through the piping at 1 to 3 psig to prevent

oxidation.

• Screw Drivers 

(JIS for terminal screws,  Flat, Phillips)

• Pliers

• Wire Strippers, Cutters, and Crimpers

• Hammer

• Adjustable Wrenches

• Drill and Bits

• Hole Saw

• Utility Knife

• Drop Cloth

• Pipe Cutter / Reamer

• Acetylene Brazing Outfit

• Brazing Material —15 % silver only

• Digital Multimeter and Amp Clamp

• R-410A Flaring Tool

• Torque Wrench Set

• Dedicated R-410A Refrigerant Manifold Gauge

• Dedicated 5/16" Premium Hoses

• Nitrogen regulator (for 550# test)

• 1/4" to 5/16" Hose Adapters (if needed)

• Nitrogen Tank

• Electronic Leak Detector

• 5/16" Schrader Core Removal Tool

• Vacuum Micron Gauge

• Good Quality Digital Charging Scale

• Vacuum Pump and Fresh Oil

• Refrigerant Recovery Unit and Tank

• Wall thickness must meet local code requirements and be

approved for a maximum operating pressure of 551 psi.

• LG recommends soft copper use to be limited to 1/2 inches.

Use hard drawn for larger sizes to avoid sags and kinks that

lead to oil trapping.

NOTE

!

Proper R-410A Flare.

Heat Recovery Outdoor Unit Service Port Diagram.

Heat Pump Outdoor Unit Service Port Diagram.

1

2

3

6

5

4

1

2

3

6

5

4

Summary of Contents for Multi V Water V ARWM072CAS5

Page 1: ...ENGINEERING MANUAL Variable Refrigerant Flow Water Source Outdoor Units 6 0 to 48 0 Tons ...

Page 2: ...serious injury CAUTION This symbol indicates a potentially hazardous situation which if not avoided may result in minor or moderate injury This symbol indicates situations that may result in equipment or property damage accidents only This symbol indicates an action that must not be performed Unit Nomenclature 4 LG Air Conditioner Technical Solution LATS 5 6 Refrigerant Charge Worksheet 7 Water So...

Page 3: ...out and validate LG Multi V Variable Refrigerant Flow VRF Multi F Multi F MAX Single Zone and Energy Recovery Ventilator ERV systems directly into CAD drawings LATS Revit integrates the LG LATS program with Revit software It permits engineers to layout and validate Multi V VRF systems directly into Revit drawings AutoCAD and Revit are both registered marks of Autodesk Inc Features All LG product d...

Page 4: ... check to see if Y Branches will also need to be changed Changes to outdoor unit and indoor unit capacities Capacities changes may impact line length changes Additional refrigerant charge quantity Trim Charge Trim charge will change if piping lengths and diameters change The As Built version must reflect installed piping lengths to ensure correct trim charge All documents submitted by the contract...

Page 5: ...ting Laboratories ETL and bear the ETL label Wiring in these units are in accordance with the National Electrical Code NEC Temperature Ranges Heat Pump Configuration In Heat Pump configuration the system can operate in heating only mode with an entering water temperature EWT of 14 F to 113 F Heat pump units can operate in cooling only mode with an EWT of 23 F to 113 F Heat Recovery Configuration I...

Page 6: ... versions of LG s indoor units and water source units are designated Generation 4 Gen 4 For Gen 4 units to operate with Gen 4 features the air conditioning system must meet the following requirements All indoor units heat recovery units and water source units must be Gen 4 All water source units must have Gen 5 software installed Water source units DIP switch 3 must be set to ON factory default se...

Page 7: ... FVC68D Unit Data Refrigerant Type R410A R410ARefrigerant Factory Charge lbs 9 9 9 9 9 9 9 9 9 9 Refrigerant Control Location EEV Indoor Unit Max Number Indoor Units System2 13 16 20 23 32 Sound Press dB A 3 Cooling Heating 46 48 54 54 58 Net Unit Weight lbs 348 348 348 348 348 Shipping Weight lbs 370 370 370 370 370 Communication Cables5 6 2 x 18 AWG Heat Exchanger Stainless Steel Plate Maximum P...

Page 8: ... all projects to ensure correct line sizing Designer must verify the shop drawing design against the as built design using LATS Contractor must also use LG manufactured Y Branch and Header Kits only Table 3 Multi V Water V 575V Units Combination Unit Model Number 36 0 Ton ARWM432CAS5 40 0 Ton ARWM480CAS5 48 0 ARWM576CAS5 Individual Component Model Numbers ARWM144CAS5 x 3 ARWM144CAS5 x 2 ARWM192CAS...

Page 9: ...1 6 14 5 25 16 0 ARWM192CAS5 1 14 2 17 8 30 20 0 ARWM240CAS5 2 7 6 11 6 14 5 9 5 25 15 24 0 ARWM289CAS5 2 11 6 11 6 14 5 14 5 25 25 28 0 ARWM337CAS5 2 14 2 11 6 17 8 14 5 30 25 36 0 ARWM432CAS5 3 11 6 11 6 11 6 14 5 14 5 14 5 25 25 25 40 0 ARWM480CAS5 3 14 2 11 6 11 6 17 8 14 5 14 5 30 25 25 48 0 ARWM576CAS5 3 14 2 14 2 14 2 17 8 17 8 17 8 30 30 30 Multi V Water V 575V Unit Specifications ELECTRIC...

Page 10: ...G is a registered trademark of LG Corp Single Frame Heat Pump and Heat Recovery DIMENSIONS Dual Frame Heat Pump and Heat Recovery DIMENSIONS Job Name Location ARWM072CAS5 Multi VTM Water 5 Heat Pump Heat Recovery 6 Ton Water Source Unit Tag No Date PO No Job Name Location Tag No Date PO No Page 2 of 2 For continual product development LG reserves the right to change specifications without notice A...

Page 11: ...a Inc North York ON Canada All rights reserved LG is a registered trademark of LG Corp Triple Frame Heat Pump and Heat Recovery DIMENSIONS WIRING DIAGRAMS 6 8 10 12 16 Tons Multi V Water V 575V Job Name Location Tag No Date PO No Page 2 of 2 For continual product development LG reserves the right to change specifications without notice ARWM576CAS5 Multi VTM Water 5 Heat Pump Heat Recovery 48 Ton W...

Page 12: ... Pressure Sensor Strainer Check Valve Service Valve 4 Way Valve Solenoid Valve Temperature Sensor High Pressure Liquid High Pressure Vapor Low Pressure Vapor M M S S Sub Cooling HEX EEV EEV Water Outlet pipe Water Inlet pipe Plate HEX Water Outlet Temp Outside Air Temp REFRIGERANT FLOW DIAGRAMS Multi V Water V Heat Pump Config Heating Operation 575V 6 8 10 12 16 Ton M M S EEV EEV Sub Cooling HEX I...

Page 13: ...ve High Pressure Sensor Water Out Water In Water Outlet Temperature Sensor Sub Cooling HEX REFRIGERANT FLOW DIAGRAMS 575V 6 8 10 12 16 Ton Multi V Water V Heat Recovery Config Heating Operation s s s s s s s s s s s s HR unit HighTemperature High Pressure Liquid HighTemperature High Pressure Vapor LowTemperature Low Pressure Vapor IDU HEX IDU Flare Joint Flare Joint M EEV IDU HEX IDU Flare Joint F...

Page 14: ...nt Flare Joint M EEV IDU HEX IDU Flare Joint Flare Joint M EEV IDU HEX IDU Flare Joint Flare Joint M EEV s Remarks Check Valve EEV Solenoid Valve Pressure Sensor Strainer Temperature Sensor SVC Valve Pressure Switch S C h a r g i n g P o r t REFRIGERANT FLOW DIAGRAMS 575V 6 8 10 12 16 Ton Multi V Water V Heat Recovery Config Heating Based Simultaneous Operation Heating ON Heating ON Heating ON Coo...

Page 15: ... a l v e H i g h P r e s s u r e Se n s o r W a t e r O u t W a t e r I n W a t e r O u t l e t T e m p e r a t u r e Se n s o r H i g h P r e s s u r e V a p o r P i p e L o w P r e s s u r e V a p o r P i p e L i q u i d P i p e C h a r g i n g P o r t REFRIGERANT FLOW DIAGRAMS 575V 6 8 10 12 16 Ton Multi V Water V Heat Recovery Config Oil Return Heating ON Heating ON Heating ON Cooling ON HR un...

Page 16: ...0 ton 59 ARWM432CAS5 36 0 ton 59 ARWM480CAS5 40 0 ton 61 ARWM576CAS5 48 0 ton 63 Measurement taken 3 3 above finished floor and at a distance of 3 3 from face of unit Measurements taken with no attenuation and units operating at full load normal operating condition Sound level will vary depending on a range of factors such as construction acoustic absorption coefficient of particular area in which...

Page 17: ...s Canada Inc North York ON Canada All rights reserved LG is a registered trademark of LG Corp Multi V Water V 575V continued ARWM288CAS5 ARWM336CAS5 ACOUSTIC DATA Sound Pressure Levels ARWM432CAS5 ARWM480CAS5 HEAD LOSS BY WATER FLOW Multi V Water V 575V Systems ARWM576CAS5 Multi V Water V 575V Models ARWM072CAS5 ARWM096CAS5 ARWM 121CAS5 ARWM144CAS5 ARWM192CAS5 0 2 4 6 8 10 12 14 0 10 20 30 40 50 6...

Page 18: ...2 12 7 I D 3 8 9 52 X2 4 5 16 110 I D 1 25 4 I D 3 4 19 05 I D 3 4 19 05 I D 7 8 22 2 I D 1 25 4 I D 1 25 4 I D 7 8 22 2 13 5 8 346 14 15 16 379 3 3 4 96 3 2 3 3 2 I D 7 8 22 2 I D 1 2 12 7 I D 1 4 6 35 4 5 16 110 O D 1 1 8 28 58 I D 7 8 22 2 4 1 2 115 X2 3 15 16 100 O D 5 8 15 88 I D 1 2 12 7 2 3 4 70 O D 7 8 22 2 I D 5 8 15 88 I D 3 4 19 05 4 3 4 120 O D 1 1 2 38 1 I D 1 3 8 34 9 I D 1 1 8 28 58...

Page 19: ...or Dual Frame Systems ACCESSORIES Outdoor Unit Y Branches Outdoor Unit Y branches for Heat Recovery Configuration For Dual Frame Systems For Triple Frame Systems ACCESSORIES Outdoor Unit Y Branches Combination specification Combination specification Low pressure Vapor Pipe Liquid Pipe High pressure Vapor Pipe Multi frame Connector ARCNB21 ARCNB21 ARCNB31 Liquid Pipe Unit inch Unit inch Low pressur...

Page 20: ...15 16 5 15 16 4 3 4 4 3 4 14 3 16 I D 3 8 I D 3 8 I D 1 4 I D 1 4 I D 3 8 I D 1 2 Headers for Heat Pump and Heat Recovery Configuration Headers ACCESSORIES LG headers serve as central connections for multiple runout pipe segments terminating at indoor units Headers must be used with LG systems and be properly installed following the instructions in the applicable LG manual Field supplied headers a...

Page 21: ...ard PCB using an accessory cable without the need for a separate interface device The main screen for LGMV allows the user to view the following real time data on one screen Additional screens can be accessed by tabs on the main screen 1 Cycleview Graphic of internal components including 2 Graph Full screen graph of actual high and low pressures and high and low pressure limits A sliding bar enabl...

Page 22: ...ELECTRICAL CONNECTIONS System for Heat Pump Configuration on page 42 System for Heat Recovery Configuration on page 43 DIP Switch Settings For Use With Gen 4 Indoor Units on page 44 ...

Page 23: ...r Outdoor Unit Communication Terminal Block Master Outdoor Unit Communication Terminal Block Slave 1 Outdoor Unit Communication Terminal Block Slave 2 Outdoor Unit Communication Terminal Block IndoorUnit IndoorUnit ODU IDU CENTRAL ODU IDU CENTRAL For Heat Recovery Unit information refer to the applicable Engineering Manual on www lghvac com Figure 9 Example of a Typical Heat Pump Configuration Pow...

Page 24: ...NLY ust be ON System will operate WITH Gen 4 indoor unit features Gen 4 or Higher Gen 4 ONLY odel 2A ONLY OFF System will operate but WITHOUT Gen 4 indoor unit features Gen 4 or Higher Gen 4 ONLY Any combination of odels 1A 2A ust be O factory default Does NOT include Gen 4 features System will not operate if DIP Switch No 3 is ON and an error code will be generated Gen 4 or Higher Any combination...

Page 25: ...WATER LOOP CIRCUIT DESIGN Water Design Guide on page 46 Water Circuit Installation on page 50 ...

Page 26: ...o u r ce U n i t s I n t e r l o ck O p e r a t i o n R o o m 1 R o o m 2 R o o m 3 5 9 F 6 8 F 5 9 F 68 F M e ch a n i ca l R o o m WATER DESIGN GUIDE Water Heating Cycle Diagram WATER DESIGN GUIDE Design Steps A Multi V Water 5 575V system requires a water cooling heating source This year round heating and cooling system must have a two pipe closed loop water circuit that circulates water contin...

Page 27: ...rs in the water loop especially if the water temperature is operated above 104 F Ensure all air is purged from the system Maintain the following levels Item Closed Type System Effect Circulating Water Supplemented Water Corrosion Scale Basic Items pH 77 F 7 0 8 0 7 0 8 0 O O Conductivity 77 F mS m Below 30 Below 30 O O Chlorine ions mg Cl L Below 50 Below 50 O Sulfate ions mg SO4 2 2 L Below 50 Be...

Page 28: ...rly or parts other than those specified by LG are used there is risk of fire electric shock explosion and physical injury or death WARNING WATER CIRCUIT INSTALLATION Pipe Insulation Water pipe insulation is suggested in the following conditions Where water pipe is subject to freezing Water pipe where water can condense on surface of pipe from ambient room temperatures higher than temperature of wa...

Page 29: ...ot share the electrical circuit with other devices There is risk of fire electric shock and physi cal injury or death due to heat generation Do not use damaged or loose power wiring Do not modify or extend the outdoor unit s power wiring randomly Ensure that the power wiring will not be pulled nor weight be placed on the power wiring during operation There is risk of fire electric shock and physi ...

Page 30: ...onnector Flow S witch S erv ice Valv e S erv ice Valv e Valv e Power 24V and Control Pressure G auge Pressure G auge Thermometer Thermometer S hutoff Valv e S hutoff Valv e Condenser Water S upply Condenser Water Return Variable Water Flow Valve Control Kit for Dual Frame Piping System Specifications WATER CIRCUIT INSTALLATION Configuring Variable Water Flow Valve Control Kit for each WSU LG recom...

Page 31: ...Panel Boiler V2 T2 Pump H eat E x changer Plate Ty pe M ulti V Water IV Unit T1 Intermediate Water H eat E x changer Refrigerant Piping System Specifications WATER CIRCUIT INSTALLATION Figure 23 Variable Water Flow Valve Control Kits for Triple Frame S hutoff Valv e 50 M esh S trainer Flex Connector Flow S witch PWFCK N0001 PWFCK N0001 PWFCK N0001 S erv ice Valv e S erv ice Valv e 1 Variable Water...

Page 32: ...PING LIMITATIONS For Systems Designed for Heat Pump Configuration Following pages present Multi V Water V piping limitations and are for illustrative purposes only Designers MUST use LATS when designing LG VRF systems Length Total pipe length Longest actual pipe length Equivalent pipe length1 A ΣB ΣC 1 640 feet 656 feet 738 feet ℓ Longest pipe length after first branch 131 feet 295 feet conditiona...

Page 33: ...ed main pipe A diameters as indicated by outdoor unit capacity Example When an indoor unit combination ratio of 120 is connected to a 20 ton outdoor unit 24 tons and indoor unit with a 7 000 Btu h capacity is located at the first branch 1 ain pipe A diameters on a 20 ton outdoor unit 1 1 8Ø inches vapor and 5 8Ø inches liquid 2 Pipe diameters between first and second branches however are 1 3 8Ø va...

Page 34: ... of the tube Drawn temper rigid ACR copper tubing is available in sizes 3 8 through 2 1 8 inches ASTM B 280 clean dry and capped Annealed temper soft ACR copper tubing is available in sizes 1 4 through 2 1 8 inches ASTM B 280 clean dry and capped Handling the Piping To avoid operation failure a VRF system CANNOT have contaminants or moisture in the piping network Piping must be kept clean dry and ...

Page 35: ...plicable Engineering Manual on www lghvac com WSU Water Source Unit HRU Heat Recovery Unit IDU Indoor Unit A Main Pipe from Water Source Unit to First Y branch B HRU to HRU Y branch to HRU HRU to Header or Y branch to Y branch C Heat Recovery Unit Header to Indoor Unit Example of Pipe Sizing When Installing a Heat Recovery System Example Triple frame system four 4 heat recovery units one 1 header ...

Page 36: ...performances to fluctuate Y branches and other header branches cannot be installed downstream of the initial header branch PIPING LIMITATIONS For Systems Designed for Heat Recovery Configuration Following pages present Multi V Water V piping limitations and are for illustrative purposes only Designers MUST use LATS when designing LG VRF systems Slave 2 Slave 1 Master To Heat Recovery Units A1 A2 A...

Page 37: ...ixed points provisions must be provided to allow pipe expansion to naturally occur generally by expansion Loops or U bends Flaring the Piping When flaring the piping use a dedicated R 410A flaring tool use only synthetic oil between the nut and the flare not inside the piping to achieve correct torque and prevent leaks Flares must be deeper to handle the higher pressures of R 410A When brazing the...

Page 38: ...o not install the unit in a location where acidic solution and spray sulfur are often used as it can cause bodily injury or death Do not use the unit in environments where oil steam or sulfuric gas are present as it can cause bodily injury or death Water source units are not weatherproof Always install water source units indoors Failure to follow this installation guideline can create an electrica...

Page 39: ...isk of the product falling and causing physical injury WARNING Place a protective cloth or other soft material at the locations where the casing comes in contact with the lifting straps to prevent damage to painted surfaces Figure 38 Moving requirements for water source units Water Source Unit s Single Frame Installation Install single frame water source units as shown Anchor bolt locations for in...

Page 40: ...ics Canada Inc if the available space is less than the space shown in these figures If water piping passes along the side of a frame ensure the indicated space is available after considering the space taken by the piping Ensure that the floor chosen location has enough strength to support the weight of the unit s If it does not have sufficient strength the unit s may fall and cause physical injury...

Page 41: ...20001747 ISO 9001 2008 LG ELECTRONICS INC EM_MultiV_WaterV_575V_10_1 LG Electronics Canada Inc Air Conditioning Technologies 20 Norelco Drive North York Ontario M9L2X6 http www lgvrf ca ...

Reviews: