Test 1
Check ignitor circuit for correct resistance
.
Remove 4-pin plug from control.
Check ohms reading across terminals 2 and 4.
See table 7. If value is correct, this is the only test
needed. If the reading on the meter is not correct, (0 or
infinity) then a second test is needed.
Test 2
Check ignitor for correct resistance
.
Seperate the 2-pin jack-plug near the manifold and check
resistance of ignitor at the plug. See table 7. If the
reading is correct, then the problem is with the wiring
between the jack-plug and the control. If reading is not
correct, the issue is the ignitor.
Test 3
Check ignitor for correct voltage
Insert meter probes into terminals 2 and 4 (use small
diameter probes in order not to damage plug).
Check voltage during 20 second ignitor warm up period. See
table 7. If voltage reads below these values, check for
correct supply voltage to furnace.
Test 1
Test 2
Test 3
Integrated Control Detail
Integrated Control Detail
Integrated Control Detail
Integrated Control Detail
IGNITOR CHECKS
Multi−Meter
(set to ohms)
Multi−Meter
(set to ohms)
Multi−Meter
(set to VAC)
Control
Ohms
103085
100973
24 to 47
39 to 70
V 10%
120
95
TABLE 7