27
1. Connect the gnav bar to the slider at the front end of the boom (see
picture 4.13). Note: the slider fitted may look different to the picture but
it still works in the same way.
2. Connect the front of the boom to the gooseneck on the mast (see
picture 4.14).
3. Connect the upper end of the gnav bar to the bracket on the mast
above the gooseneck (see picture 4.15).
4. Feed the gnav control line down through the swivel block and cleat
below the boom and tie a stopper knot in the end of the rope (see
picture 4.16).
Picture 4.13 Connecting the gnav to the boom.
Picture 4.14 Connecting the gnav to the mast
Picture 4.15 The gnav control line.
Picture 4.16 The gnav fully rigged.
4.7 Hoisting the jib.
To complete this section, you will require:
•
The jib.
•
The jib sheets.
•
The top furling unit and shackle.