554515_A_PUB_DATE_1_FEB_2014.DOC
INSTALLATION AND MAINTENANCE MANUAL
53
CHECKING BEFORE PUTTING INTO SERVICE
1. A check of the transport braces removal.
2. Removal of the cabinet protective foil.
3. A check if the waste sump is ready for water drainage.
4. A check of the protective connection (earth connection) - „PE“ or „PEN“.
5. A careful reading of the operation manual before the machine start and following the instructions stated.
6. Check of the drum rotation direction during extracting:
MACHINES 33-40-55 kg / 80-100-125 lb
LOOKING AT THE MACHINE FROM THE FRONT VIEW THE DRUM ROTATION DURING EXTRACTION
MUST BE COUNTER-CLOCKWISE!
MACHINES 80-100-120 kg / 180-230-275 lb
LOOKING AT THE MACHINE FROM THE FRONT VIEW THE DRUM ROTATION DURING EXTRACTION
MUST BE CLOCKWISE!
7. A check of the vibration switch function during extracting and the emergency function.