Installation
Attention :
- Do not connect to electrical supply,
- Make sure the ¼ turn valve is closed,
- Do not carry out any connection on the appliance’s inlet or
on the storage tank.
1.
Open the feed water supply, the water purifier
is under hydraulic pressure.
2.
Connect it to electrical supply.
3.
The water purifier, after a LED test, will flush
(about 30 sec.).
FLUSHING
The flushing operation should be carried out in the following cases:
•
the first time RO400C is used ;
•
put back on working after storage ;
•
after a descaling ;
•
after replacing the membrane;
4.
When the flushing finishes, disconnect and then
connect the water purifier to electrical supply.
RO400C flushes again for 30 sec.
5.
Repeat twice the previous operation to carry out
3 flushing cycles in all.
The water purifier stands-by when green ON/OFF led is lighted up.
CALIBRATION
Calibration of water purifier should only be carried out :
•
the first time the RO400C is used;
•
if the appliance is moved to a different place (so different inlet water);
•
After the membrane has been replaced.
6.
Direct the purified water hose to a drain.
Open the purified water valve and within 10 seconds press
“Calibration” button and keep it pressed till “Purification Level”
lights I and II light up and then go out.
After having released the button, the water purifier products
water without any indication of the purification level; this is the
calibration.
7.
Let the water flow till when the green «purification level III » light
lights up.
This takes about 10 minutes.
8.
When the green «level III » light lights up, close the purified water valve, a
flushing operation will start.
The flushing duration is 1/10 of the water suction time.
3x
Purge
10 mn
Open the purified
water valve.
Hose direct to a
drain