5C. INSTALLING CEILING MOUNT ON CONCRETE CEILINGS
Fixing of Master Plate:
1. Use the Paper template provided to mark the position for the anchors of Master Plate.
2. Drill the Six (6) mounting holes 14mm diameter and 100mm deep.
3. Place a 10mm flat washer and a split washer over each of the six M10 X 75 hex head RAWL Plug.
4. Keeping welded bosses downside, line up the holes of Master plate with the pilot holes in the ceiling.
5. Insert the hex head RAWL screws into the holes and tighten the Master Plate with a 17mm hex socket
spanner.
Installation of Ceiling Mount:
6. Position the ceiling Mount Provided against the master plate and insert 6 socket head bolts M12 X 40
after aligning the 6 mounting holes.
7. Tighten all the bolts using Allen key 10mm slightly.
8. Use a level to ensure the column assembly is Leveled vertically. Refer Section “Leveling the ceiling
Mount system” to correct any leveling concerns.
9. All the jobs from Part 1 to 8 here are the responsibility of the customer to provide. Labomed representa-
tive will complete rest of the microscope Installation after this.
10. Plug the support system power cord into the hospital grade earth-ground AC outlet, and verity that
there is power to the system.
11. Put the drop ceiling tile back into place.
Concrete Ceiling
Master Plate
Column
Level
Normal Ceiling Mount
Heavy Duty vibration free Ceiling Mount
Concrete Ceiling
Master Plate
Shim
Column
Level
Shim
Figure-15
Figure-16