I-40 Manual and Spark Ignition
Owner’s Manual • I-40
11
INSTALLATION LAYOUT
FOR SAFE CLEARANCES
0.91m MINIMUM
BROODER TOP TO CEILING
POSITION THE GAS HOSE AND ELECTRICAL POWER CORD
OUTSIDE OF THE HOT ZONE DIRECTLY ABOVE
THE HEATER. POSITION THE GAS HOSE AND POWER CORD
TO AVOID ANY OPPORTUNITY FOR CONTACT WITH THE HOT
CANOPY SURFACE OF THE HEATER.
MINIMUM 0.91m CLEARANCE
TO COMBUSTIBLES
FLOOR
I40 - 1.37m MINIMUM
POINT OF COMBUSTION
CONE TO FLOOR
HANG THE HEATER WITH THE
CONTROL END 1 TO 5 DEGREES DOWN
FROM HORIZONTAL (SEE BELOW)
CONTROL PANEL
GAS PIPING
ATTENTION:
■
High pressure agricultural building radiant heaters
use an integral hanging bracket with quick link for
hanging the heater.
■
Attach only steel cable or chain to the quick link.
Do not use combustible hanging materials such as
ropes, lines, etc.
■
The installer must make sure that the heater is hung
so control end of heater is positioned 1º to 5º down
from horizontal after gas supply hose is attached.
This allows proper venting of heater and eliminates
potential heat damage to optional dust
fi
lter.
■
Repositioning of factory installed quick link into hang-
ing bracket may be required.
■
Refer to following illustrations.
Installation Layout
FIG. 2
THIS
NOT THIS
CONTROL END
QUICK LINK
STEEL CABLE
HANGING
CONTROL END
OR CHAIN
BRACKET
OF HEATER
MUST BE 1 TO 5 DOWN
FROM HORIZONTAL
3 FT. MINIMUM BROODER
TOP TO CEILING
POSITION THE GAS HOSE AND ELECTRICAL POWER CORD
OUTSIDE OF THE HOT ZONE DIRECTLY ABOVE THE HEATER.
POSITION THE GRAS HOSE AND POWER CORD TO AVOID
ANY OPPORTUNITY FOR CONTACT WITH THE HOT CANOPY
SURFACE OF THE HEATER.
MINIMUM 3 FT.
CLEARANCE
TO COMBUSTIBLES
FLOOR
I-40: 4.5 FT.
MINIMUM POINT OF
COMBUSTION CONE
TO FLOOR
HANG THE HEATER WITH THE CONTROL
END 1 TO 5 DEGREES DOWN FROM
HORIZONTAL (SEE BELOW)