Krups XP7200 Series Servicing Manual Download Page 15

Grinder not compliant 
Too much ground coffee: 
cakes >17mm 
Not enough ground coffee < 
6mm 

Measure the cake 
thickness:  
12 to 15 mm (11 to 13 mm 
if grinder new) 

Grinder 

Ground coffee 
clogged up in the 
chamber 

Bad electronics grinding time 
setting with regards to grinder 
specifications 

Adjust electronics 

 

 

Ejection plunger stuck in high 
position 

Identify the cause of 
sticking: 

- Clean or replace 
- Replace ejection ram 
spring 6.5 N 

Î

 13N (to be 

done before 17 Nov.) 

- excessive chafing of the 
ejection pin "Barista" seal? 
- ground coffee blocked 
between interface and 
tank? 

- Check the state of the 
tank bottom on the Barista 
seal seating 

Ejection ram does not return 
far enough up 

- Ejection plunger rod too 
short (up to 4 mm!) 

Change ejection rod 

- Retraction pin disengages 
before reaching the high 
position  

Cakes placed in columns in 
the cake tray 

 

Install a modified cake tray 
with ribbing inside 

Actuator switch short-circuited 
+ 2-cup cycle (grinding 
without tamping head in the 
high position) 

 Change 

the 

switch 

Ground coffee blocked 
between tamping head and 
grinder spout 

 

Insert power board with 
drain time extended from 8 
to 10 secs (> V21 picto 
and > V14 graphic) 

Bad thermoblock drain 
Leakage at tamping head seal 
level 

Check that the tamping 
head does not catch the 
grinder spout when it 
comes back up 

Change the seal 
Change the grinder spout 
 

Coffee grounds collector 
replaced partially full 

 

 

Temperature too high 

See "vaporize" problem 

 

Coffee made after steam pre-
heating without steam actually 
being produced 

 

 

Nozzle overflow at 
coffee outlet 

Creamy seal defective 

 

Creamy seal 

Coffee leakage 
under the 
thermoblock 

"Barista" seal defective or 
dislodged 

Remount the seal 

"Barista" seal 

Clean the excess of grease 
in the tank and under the 
ejection plunger 
Take up seal slack 

Not enough cream 
on the coffee 

Defective "creamy" seal 

 "Creamy" 

seal 

Steam nozzle adaptor before 
15/10/2005 (diam 1.3) 

Steam nozzle adaptor 
(diam 1.15) 

Faulty draw switch 
control 

Grinder mounting spacer 
missing 

Î

 the mounting 

screw goes through the 
screwing bushing and blocks 
the draw control 

Replace spacer 

 

Minimum level in the 
tank not detected 

Electronic detection circuit 
positioned too low 

Remount the circuit by pulling 
and slightly tightening the 
wires 

Change the tank receptacle 
(modified mid-Nov. 2005) 

 

15

Summary of Contents for XP7200 Series

Page 1: ...2 electronic boards for o thermoblock temperature regulation o mesuring the waterflow volume by counting flowmeter pulses o 1 cup 2 cup hot water graphic model steam cleaning and scale removal cycle...

Page 2: ...cing Facing mount mount Grinder Tamping head Control board if necessary replace board Power board Pump Flowmeter Thermoblock actuator Fuses Distributor Steam nozzle Coffee nozzle Body provides visual...

Page 3: ...by pressing on the top nut using a socket spanner or equivalent Disassemble the switch control plate Flowmeter No particular instructions Power electronic board Electronic circuit mount maintained in...

Page 4: ...onnect the distributor thermoblock coffee hose from the distributor Disconnect the thermoblock distributor steam hose from the thermoblock system if necessary remove the drain from the distributor aft...

Page 5: ...be replaced Use Norma Cobra 7 5 clamps Lock the clamps with gripping pliers and check that they have been properly assembled Grinder Indexing and mounting of the grinder ring on the coffee maker are t...

Page 6: ...embly line same as for V16 except that setting operation is carried out before the standard coffee cycle With cake tray draw and tank removed Press steam key mains connection o Blue On Off light comes...

Page 7: ...lay 1 2 3 4 5 Time for strong coffee grinding secs 6 7 8 9 10 grinder 2 15 02 2006 Lead Respect the earthwire routing The lead earthwire must not be in contact with moving parts stainless steel corner...

Page 8: ...When screwing be careful not to offset the tamping head mount Thermoblock and ejection scraper interface Take care when replacing the seal which must not protrude into the coffee chamber Distributor R...

Page 9: ...ghten counterclockwise Electronic boards Connectors on electronic boards check that connectors are well secured by the clips Check the coffee volume selector button for correct indexation 1 2 turn pos...

Page 10: ...see troubleshooting diagnosis table grinder not compliant quantity of ground coffee electronics setting not compliant with the grinder ejection ram stuck in high position cake tray replaced partially...

Page 11: ...maximum time for the ground coffee distributor has been reached without the ground coffee proportioning switch being detected Concerns the ground coffee version 3 3 Cycle start conditions The distrib...

Page 12: ...tank or with tank empty Water level board or bundle defective 8 8 Hot water and Coffee Pump After a certain time of pump control during coffee or water flow the circuit is considered to be blocked as...

Page 13: ...use which led to the coffee leaking Interface tank seal Thermoblock or water circuit scaled up Remove scale Replace scaled up item if scale removal ineffective Thermoblock coffee circuit clogged up by...

Page 14: ...circuit Volume of coffee in the cup does not comply Thermoblock or water circuit scaled up Remove scale Replace scaled up item if scale removal ineffective A few drops of water drip from the steam noz...

Page 15: ...ad and grinder spout Insert power board with drain time extended from 8 to 10 secs V21 picto and V14 graphic Bad thermoblock drain Leakage at tamping head seal level Check that the tamping head does n...

Page 16: ...consumption of distributor motor distributor opposing torque too high Risk of damage to the electronic power board AFTER SALES A S MODE OPERATION 1st level A S mode This mode makes it possible to acc...

Page 17: ...Times switched on number unit 13 Operating time min ON OFF light on 14 Rinsing number unit 15 Auto cut off duration 1 2 3 4 5 hours hour 16 Water hardness scale removal frequency level 0 1 2 3 4 valu...

Page 18: ...r No 13 Production date 14 First use date 15 Graphic software version Ref 16 Power software version Ref 17 Model grinder Model 18 Coffee function water volume ml 19 Steam function water volume ml 20 T...

Page 19: ...19...

Page 20: ...correct operation of switches for detecting the presence of draw cake tray and tank Correct coffee operation with measurement of cake thickness comprised between 11 and 13 mm with new grinder in 60 m...

Reviews: