Heat Transfer Kit(s)
SECTION 3
FRAMING
#SFD-36
R.6 February 2022
21
HUSSONG MFG. CO., INC.
KOZY HEAT FIREPLACES
3.7.2 Heat Transfer Kit Installation Requirements
You will not be able to install at minimum horizontal venting if you
are planning to install (2) heat transfer kits. The vertical vent height
length must be increased. See
.
If using (1) heat transfer kit, the vent termination must be on the
opposite side of the heat transfer kit air chute. See
.
Corner installations have different minimum requirements to allow
space for the installation of the SFD-HTK air chute. See
71
1⁄8
”
(1807mm)
36
¾
”
(933mm)
35”
(890mm)
50
¼
”
(1277mm)
½
”
(12mm)
15
7⁄8
”
(403mm)
Typical Corner Installation with (1) Air Chute Installed
FIGURE 3.10
Typical Corner Installation Minimum Dimensions with (1) Air Chute
FIGURE 3.9
Corner Installation Vertical Vent Height with (2) Heat Transfer Air Chutes