Test operation
11. Test operation
11.1 The test operation must be carried out after the entire installation has been
completed.
11.2 Please confirm the following points before the test operation.
The indoor unit and outdoor unit are installed properly.
Tubing and wiring are correctly completed.
The refrigerant pipe system is leakage-checked.
The drainage is unimpeded.
The ground wiring is connected correctly.
The length of the tubing and the added stow capacity of the refrigerant have been recorded.
The power voltage fits the rated voltage of the air conditioner.
There is no obstacle at the outlet and inlet of the outdoor and indoor units.
The gas-side and liquid-side stop val
v
es are both opened.
The air conditioner is pre-heated by turning on the power.
11.3 T
e
st operation
Set the air conditioner under the mode of "COOLING" by remote controller, and check the following points.
Indoor unit
Whether the switch on the remote controller works well.
Whether the buttons on the remote controller works well.
Whether the air flow louver moves normally.
Whether the room temperature is adjusted well.
Whether the indicator lights normally.
Whether
the
temporary buttons works well.
Whether the drainage is normal.
Whether there is vibration or abnormal noise during operation.
Outdoor unit
Whether there is vibration or abnormal noise during operation.
Whether the generated wind, noise, or condensed of by the air conditioner have influenced your
neighborhood.
Whether any of the refrigerant is leaked.
102
Summary of Contents for KV 24CC-ARF21
Page 1: ......
Page 5: ...3...
Page 13: ...Dimensions 2 Dimensions Unit mm MODEL A B C H KV24CC ARF21 230 15 9 9 52 260 11...
Page 14: ...Service Space 3 Service Space 1000mm 1000mm 1000mm 1000mm 12...
Page 15: ...Wiring Diagrams 4 Wiring Diagrams KV24CC ARF21 13...
Page 21: ...Field Wiring 11 Field Wiring KV24CC ARF21 19...
Page 27: ...Dimensions 2 Dimensions Capacity Btu h A H 36 245 275 48 245 275 25...
Page 28: ...Service Space 3 Service Space 1000mm 1000mm 1000mm 1000m m 26...
Page 29: ...Wiring Diagrams 4 Wiring Diagrams KV36CC ARF21B KV48CC ARF21B 27...
Page 34: ...Field Wiring 9 Field Wiring KV36CC ARF21B KV48CC ARF21B 32...
Page 36: ...34...
Page 38: ...Service Space 3 Service Space 36...
Page 39: ...Wiring Diagrams 4 Wiring Diagrams KV24CM ARF21 37...
Page 46: ...Field Wiring 11 Field Wiring KV24CM ARF21 44...
Page 48: ...46...
Page 50: ...Service Space 3 Service Space 48...
Page 51: ...Wiring Diagrams 4 Wiring Diagrams KV36CM ARF21B KV48CM ARF21B 49...
Page 54: ...Field Wiring 9 Field Wiring KV36CM ARF21B KV48CM ARF21B 52...
Page 56: ...54...
Page 58: ...Service Space 56 GA Floor standing Type 3 Service Space 56...
Page 59: ...Wiring Diagrams 4 W iring Diagrams KV36FM ARF21 KV60FM ARF21 57...
Page 62: ...Accessories 7 Accessories 60...
Page 64: ...Field Wiring 9 Field Wiring KV36FM ARF21 KV60FM ARF21 62...
Page 70: ...Wiring Diagrams 4 Wiring Diagrams KV24ODU ARF21 220075301510 KV24ODU ARF21 220075301740 68...
Page 71: ...Wiring Diagrams KV36ODU ARF21 B 220075501730 KV36ODU ARF21 B 220075502120 69...
Page 72: ...Wiring Diagrams KV48ODU ARF21B 70...
Page 73: ...Wiring Diagrams KV60ODU CRF21 71...
Page 113: ...Troubleshooting 2 1 5 Display board of Floor standing 111...
Page 118: ...2 4 1 2 Outdoor unit malfunction 116...
Page 121: ...Troubleshooting Electrical Control System 2 4 2 2 E2 malfunction 119...
Page 122: ...2 4 2 3 E3 malfunction 120...
Page 126: ...2 4 2 7 P1 malfunction Only for 36K 52K 124...
Page 127: ...Troubleshooting 2 4 2 8 P2 malfunction Only for 36K 52K 125...
Page 128: ...2 4 2 9 P3 malfunction 126...
Page 131: ...Troubleshooting 2 4 2 12 P6 malfunction For single phase units 129...