MAINTENANCE PROCEDURES
MAINTENANCE
4-70
Accumulator operation check
CAUTION
Before starting check operations, make sure that no person or other obstacles are in the surrounding
area.
Check nitrogen loading pressure as follows.
1.
Stop the machine on a solid and flat surface.
2.
Place the working tool as extended as possible (fully
extended boom and bucket in discharge position) and keep
it 1.5 m (A) away from the ground.
REMARK
Carry out the operations described in points 3-5 within 15
seconds.
Pressure in the accumulator descends gradually when the
engine is stopped. Therefore, the check must be carried out
immediately after the engine is stopped.
3.
Keep the working tool at the maximum distance, turn the
start-up key to OFF and stop the engine.
4.
Turn the starter key to ON.
WEAM014500
Summary of Contents for PC22MR-3
Page 2: ......
Page 3: ...FOREWORD 11 WEAM014500...
Page 5: ...FOREWORD FOREWORD 1 3 Storage location for the Operation and Maintenance Manual WEAM014500...
Page 88: ...SAFETY MAINTENANCE INFORMATION SAFETY 2 60 WEAM014500...
Page 208: ...TROUBLESHOOTING FUNCTIONING 3 120 WEAM014500...
Page 226: ...LUBRICATION MAINTENANCE 4 18 BALL BEARING RING GREASING POINTS 4 Grease WEAM014500...
Page 281: ...SPECIFICATIONS 15 WEAM014500...
Page 290: ...LIFTING CAPACITIES SPECIFICATIONS 5 10 WEAM014500...
Page 310: ...BUCKET WITH HOOK OPTIONAL EQUIPMENT 6 20 WEAM014500...
Page 311: ......
Page 312: ...2011 KOMATSU UTILITY EUROPE S p A All Rights Reserved Printed in Europe 02 2011...