Install the receptor with the
drain fitting attached
3. Receptor Only Installation
-
Assemble and install the drain according to the manufacturer’s instructions.
-
Move the shower receptor into the framing pocket.
-
Make sure the unit is level on all three sides. If the unit is not level, the back of the base will need to be shimmed
as required to level the unit.
-
Predrill the side and back nail-in flanges on the stud centers around the receptor. Do not nail the receptor in place
at this time.