25
5.5 Initial start-up of the grinding machine
Place the grinding machine at the installation site on a level base.
Compensate for any unevenness in the floor using the adjustable machine feet by unscrewing
them counterclockwise. The machine is aligned using a level.
Have an authorized electrician install the current supply on-site.
Completely install and inspect the protective equipment before commissioning.
Have all protective equipment checked for proper functioning by
authorized trained personnel before commissioning the machine.
CAUTION
Have the compressed air supply installed on site by a qualified technician.
Confirm that the machine is correctly connected to the pressurized air
supply.
If connected incorrectly, pressurized air may leak, causing parts to spin
and potentially injure someone.
Observe local safety and accident prevention regulations for pressurized
air.
CAUTION
5. Installation