Start-up guideline
4.3
Commissioning guideline for the multicomp F144-3PH
Start menu Commissioning:
If the multicomp is being commissioned for the first time, the menu Extra /
Commissioning is displayed as the start screen (after the initialization phase)
after setting up the supply voltage:
commissioning
transformers
cosÓ
Stage parameter
max. switch. pwr
¡
¯
Enter
This display is used for the initial commissioning of the controller, where all the
necessary settings can be made.
Controller preconfigured:
If a controller already integrated into a KBR compensation unit by default
should be used, only the parameters of the current transformer have to be
configured.
1. Configuring current transformer values
For the compensation controller to function properly, all current transformer
parameters have to be set correctly. Primary and secondary current of the
transformer have to be set. These parameters can be read on the nameplate of
the current transformer. In addition, the phase allocation of the transformer has
to be set correctly. In the controller, the phase (L1, L2, L3) in which the current
transformer is integrated has to be set. This setting does not have to be made
for 3-phase measurement.