V003. 25.06.2002
B-35
12) Turn on the primary mains switch that is on the control panel of the first cabinet.
13) Turn on the primary battery switch that is on the control panel of the first cabinet.
14) Turn on the fan switches that are on the control panels of the cabinets. The fans must
be working while the system is in operation.
After being powered, the system carries out a series of automatic tests in order to check the
current configuration. Beginning with the card in the rightmost slot, two LEDs that are on the
front plastic panel of each card start to light in a row. This action begins with the bottom
rack.
After the entire LEDs have begun to light, the message “connecting” appears on LCD screen
of LT200 (-H) or FT20 feature telephone that is connected to the system. Once that message
disappears, the system is ready to operate.
!
WARNING
1) In order to turn on and off a cabinet-type system, use the
mains and battery switches that are in front of the cabinet.
2) The correct way of powering the system is putting the
batteries on line after turning the system on.
3) The correct way of shutting down the system is putting the
batteries off line before turning the system off.