DS200 Installation Guide
DS200 Installation Guide
DS200 Installation Guide
DS200 Installation Guide
V003. 25.06.2002
B-2
The lower hole of the wall mount bars should be approximately 130 cm. above the floor. It
is essential to check whether the height of both holes are the same, in order to make
sure the exchange is parallel to the floor.
3- If there are two DS200 racks to be installed, then the lower hole of the wall mount bars,
for the first rack to be installed (That will be the lower rack.), should be 100 cm. above
the floor.
4- Drill the lower wall mount bar hole of the second rack 140 cm. above the floor, vertically
on the same line with the first one. When the installation is over, there will be a 10-cm
gap between the two racks.
Figure – 1
5- Drive the anchor plugs into the holes, whose locations have already been checked, and
then screw the wall mount bars. Note that the right and the left side of the wall mount
bars differ. The screws must be fixed enough to burry their heads completely into the
wall.
6- After removing the front cover of the exchange by unscrewing the Allen screws, remove
the bottom cover by sliding it to the front.
7- While removing the bottom cover, watch out for the grounding cables that are between
the cover and the main frame, so that they will not break off. Remove the cables from the
covers together with their tags and keep them safe from any damage during the
installation.
8- Slide the SPS200 to the front and remove it, after loosening its screws. (This is just for
facilitating the installation and not obligatory.)