As all components are factory-fitted, at the job site it is nec-
essary to merely connect the 3-way valve intake and output
to the how water line.
Turn main power supply to the unit off. See Figs. 1, 2, 3, 4
and wiring diagram for coil connection details.
Commissioning
1. Remove the access panel to the 3-way valve, side panel
motor side.
2. The water intake and outlet connections are carried out
from the front (remove the valve actuator [ref. 2] for weld-
ing and reinstall afterwards.
Attention:
It is recommendable to install manual valves
on the intake and outlet lines, so as to be able to isolate
the unit from the general installation if necessary.
3. Hot water coil control board.
The control board, the water intake probe and the air
impulse probe are factory-installed. The wiring of the
valve actuator has also been completed as per the wiring
diagram.
When installing at the job site, connect the telephone
cable between the hot water coil accessory board (J15
or J16) and the YKlon board or the board of the second
compressor located in the outdoor unit (VCH).
Also connect the 24 VAC power supply hose supplied.
Attention:
It is recommendable to install the impulse
probe (B16) in the impulse duct at one meter from the
indoor unit (VIR), for improved display and readout.
Once the water intake and outlet connections are com-
pleted, turn the power supply to the machine on.
Make sure the green LED (V1) on the coil control board
(A6) is flashing (accessory board configured).
Should this not be the case, carry out a search and con-
figuration of accessories by pressing the test button on
the Yklon board (A1) for over three seconds, until the red
LED goes on. Once this search and configuration proc-
ess begins, the red LED goes on and stays on until this
operation is completed. Once it goes off, make sure the
green LED (V1) on the coil board is flashing to indicate
the accessory has been configured.
4. Check valve actuator operation.
A potentiometer, P1, on the coil control board allows
modulating the 3-way valve manually to check its opera-
tion.
The actuator will go back to its operating position after 30
seconds.
5. Jumper S2 (ENTALP) selection
By defect, factory-set to open, selects the priority of the
compressors in heat pump models. If closed, selects
operating priority of the hot water coil over the compres-
sors. Adequate for installations with very economical hot
water.
6. Water pump operation relay output.
The control board has a relay (K1) that, through connector
J14, gives output to a volt-free contact for the operation
of an installation water pump.
VIR Unit
Hot water coil control board
Fig.1
Fig.2
Led
Status
Indication
V1
Off
Board is not connected
V1
On
Board is not in service
V1
Flashing
Normal operation
V2
On
Favourable condition
V2
Flashing
Antifreeze protection
������������
����������������
����������������
�
�
�
��
���
���
���
���
�����
���
���
��
���
���
���
��
��
��
��
Summary of Contents for York VCH 20A
Page 17: ...17 Technical characteristics General dimensions mm VCH 20A and 25A ...
Page 18: ...18 General dimensions mm VCH 30A and 40A ...
Page 19: ...19 General dimensions mm VCH 45A and 60A ...
Page 20: ...20 General dimensions mm VCH 75A and 90A ...
Page 21: ...21 General dimensions mm VIR 25A VIR 40A ...
Page 22: ...22 General dimensions mm VIR 45A and 60A VIR 75A and 90A ...
Page 23: ...23 Cooling diagram Variant chart ...
Page 31: ...31 Electric diagram VCH 20 25 30 40A 400 3 50 ...
Page 32: ...32 Electric diagram VCH 45 60 75 90A 400 3 50 ...
Page 33: ...33 Electric diagram VCH 45 60 75 90A 400 3 50 ...
Page 34: ...34 Configuration of switches ...
Page 43: ...43 Wiring diagram VIR 45 90 ...
Page 48: ...48 Wiring diagram Heater 10 15kW 400 3 50 VIR 25A 40A 45A and 60A ...
Page 49: ...49 Wiring diagram Heater 20 30 40kW 400 3 50 VIR 40A 45A 60A 75A and 90A ...
Page 59: ...59 VCH 20A to 40A VCH 45 to 90A ...
Page 61: ...61 Wiring diagrams ...
Page 62: ...62 Wiring diagrams ...
Page 69: ...69 Wiring diagram ...
Page 71: ......
Page 72: ...www johnsoncontrols com ...