JOHNSON CONTROLS
22
FORM 145.05-SU7
ISSUE DATE: 10/31/2019
SECTION 3 - PRE START-UP CHECkLIST
When using the SERVICE key each list has a * to show
the top of the respective list. Moving left or right starts
a new section within the SERVICE key.
ANALOG INPUT VERIFICATION
1. Use the information below to prove that the sen-
sors and/or transducers are reading correctly.
2. Push the SERVICE key and move to the left using
the arrow until you see SERVICE AI PIO on the
top left of the screen. This is the Analog Input list.
3. If a sensor or transducer is not reading, verify that
it should be part of the installation. Not all sensors
may be installed on the equipment. This depends
on the setup of the unit and options.
4. Record the current value.
5. Temperature sensors that are not available or con-
nected correctly read -20 degrees.
6. Transducers that are not connected correctly read
0psig.
7. Humidity sensors that are not available or con-
nected correctly read 0%.
TABLE 2 -
ANALOG INPUT VALUES
ANALOG INPUT
VALUES
Supply Air Temp Current
MX Supply Air Temp Current
Evap Press Temp Current
Flex Evap Temp Current
Water Temperature Entering
Water Temperature Leaving
Mixed Air Temp
Outside Air Temp
Return Air Temp
Outside Air Humidity
Return Air Humidity
Pressure Suction A
Pressure Suction B
Pressure Suction C
Pressure Suction D
Pressure Suction E
Pressure Suction F
Pressure Discharge A
Pressure Discharge B
Pressure Discharge C
Pressure Discharge D
Pressure Discharge E
Pressure Discharge F
Duct Static Press 1
Duct Static Press 2
Vent Override
Zone Temp Current
Underfloor Slab Temp
Underfloor Air Humidity
Summary of Contents for LSWD
Page 4: ...JOHNSON CONTROLS 4 FORM 145 05 SU7 ISSUE DATE 10 31 2019 THIS PAGE INTENTIONALLY BLANK ...
Page 10: ...JOHNSON CONTROLS 10 FORM 145 05 SU7 ISSUE DATE 10 31 2019 THIS PAGE INTENTIONALLY BLANK ...
Page 11: ...JOHNSON CONTROLS 11 FORM 145 05 SU7 ISSUE DATE 10 31 2019 SECTION 3 PRE START UP CHECKLIST ...
Page 12: ...JOHNSON CONTROLS 12 FORM 145 05 SU7 ISSUE DATE 10 31 2019 SECTION 3 pre Start Up Checklist ...
Page 13: ...JOHNSON CONTROLS 13 SECTION 3 pre Start Up Checklist FORM 145 05 SU7 ISSUE DATE 10 31 2019 ...
Page 14: ...JOHNSON CONTROLS 14 FORM 145 05 SU7 ISSUE DATE 10 31 2019 SECTION 3 pre Start Up Checklist ...
Page 15: ...JOHNSON CONTROLS 15 SECTION 3 pre Start Up Checklist FORM 145 05 SU7 ISSUE DATE 10 31 2019 ...
Page 16: ...JOHNSON CONTROLS 16 FORM 145 05 SU7 ISSUE DATE 10 31 2019 SECTION 3 pre Start Up Checklist ...
Page 17: ...JOHNSON CONTROLS 17 SECTION 3 pre Start Up Checklist FORM 145 05 SU7 ISSUE DATE 10 31 2019 ...
Page 18: ...JOHNSON CONTROLS 18 FORM 145 05 SU7 ISSUE DATE 10 31 2019 SECTION 3 pre Start Up Checklist ...
Page 19: ...JOHNSON CONTROLS 19 SECTION 3 pre Start Up Checklist FORM 145 05 SU7 ISSUE DATE 10 31 2019 ...
Page 20: ...JOHNSON CONTROLS 20 FORM 145 05 SU7 ISSUE DATE 10 31 2019 SECTION 3 pre Start Up Checklist ...
Page 30: ...JOHNSON CONTROLS 30 FORM 145 05 SU7 ISSUE DATE 10 31 2019 THIS PAGE INTENTIONALLY BLANK ...
Page 34: ...JOHNSON CONTROLS 34 ...
Page 35: ...JOHNSON CONTROLS 35 ...
Page 36: ...JOHNSON CONTROLS 36 ...
Page 37: ...JOHNSON CONTROLS 37 FORM 145 05 SU7 ISSUE DATE 10 31 2019 THIS PAGE INTENTIONALLY BLANK ...