background image

MNP85ENV00 

Rev.02 (2014-01-07)                         Page 7 of 20 

3.2  Reader behaviour when a jam is detected 

The following configurations of switches allow you to choose how the banknote reader 
should behave when there is a jam. To configure either one of them, the banknote 
reader should be off. Select the suitable switch configuration, turn on the reader and 
wait until all blue LEDs are on. You can then turn off the reader, as the setting is 
saved in the EEPROM.  
Once it is saved, you can return to the configuration of switches in normal operation 
that you had decided, with switches 7 and 8 OFF. 
 

Stack, resettable error

: When a banknote is jammed, it attempts to stack it without 

validating it so the reader can be back in service. In this situation, the only way to 
verify the truthfulness of a user claim is to rely on the machine audits to see if there 
are any uncounted banknotes in the stacker 
 

 
 
 

The other configuration is 

don´t stack, resettable error

: In this configuration the 

banknote remains in the position where it was stuck. This way you can verify that 
there has been a problem when you remove the stacker.  This way, the reader is out 
of service until the jammed banknote is removed. In this situation, you can verify the 
truthfulness of a user claim just by opening the stacker and seeing if there is a 
jammed banknote. 
 
 

SW1 SW2 SW3 SW7 SW8 

OFF ON OFF ON OFF 

 

3.3  Bill group acceptance 

Dip switches 4 and 5 (BILL GROUP ACCEPTANCE) are used to inhibit or enable 
whole groups of banknotes that have been previously loaded into the banknote 
reader. When any of the dip switches are in OFF the group is accepted, while it is ON, 
the group is inhibited. If you want to inhibit a specific banknote (not a group of 
banknotes) you have to use inhibition with a different combination of dip switches, 
explained in the next item, 'Testing and programming'. 
 

3.4  Bit time adjustments. 

Dip switch number 6, MDB ADJUST is used to adjust bit times in communication. It 
can be used in cooperation with technical support service to install the BT11 on 
special machines. 
 

3.5 Testing 

and 

programming 

To enter programming mode and communication with a PC, dip switch 8 must be 

ON and dip switch 7 to OFF. This combination of switches is mandatory if you want to 
connect the reader to a computer with the needed software installed. You don´t need 
to set this combination for any other situation unless it is specifically mentioned on this 
manual 
 
SW7 SW8 

OFF ON 

SW1 SW2 SW3 SW7 SW8 

OFF OFF  ON  ON  OFF 

Summary of Contents for BT-11

Page 1: ...MNP85ENV00 Rev 02 2014 01 07 Page 1 of 20 English BANKNOTE READER BT 11 User s Manual Jofemar...

Page 2: ...com Tel 34 948 751212 Fax 34 948 75 04 20 This symbol means there are more detailed explanations on this subject elsewhere in the manual This symbol means that the text in question refers to programm...

Page 3: ...7 3 3 Bill group acceptance 7 3 4 Bit time adjustments 7 3 5 Testing and programming 7 3 6 Bill inhibition and software information 8 3 7 Sensor calibration 8 3 8 Front LED lighting control without M...

Page 4: ...aracteristics of the banknote reader Easy access to internal parts without the need for special tools Top security stacker Easy to dismantle It can work in escrow mode so the banknote is held back so...

Page 5: ...LEDs organised by pairs 10 of them are blue and the other 4 are red When one led is said to be on it means a pair since the hardware of the reader cannot turn a single led on so there are 5 blue LEDS...

Page 6: ...8 are OFF With this selection MDB communication takes place between the banknote reader and the machine to which it is connected Selecting switches 1 2 and 3 choose one of the available LED lighting c...

Page 7: ...ervice until the jammed banknote is removed In this situation you can verify the truthfulness of a user claim just by opening the stacker and seeing if there is a jammed banknote SW1 SW2 SW3 SW7 SW8 O...

Page 8: ...ersion is indicated by the number of times the central blue LED blinks meaning that if you have installed the 5 th version of the patterns the LED will blink 5 times The software version of the reader...

Page 9: ...e the note is not validated avoiding jams or any damages to the note that is refunded This mode is available from software version BT11MD11 onwards and all the readers have this mode enable by default...

Page 10: ...itches is explained in section 3 This method should be used with new control cards provided by Jofemar or when the calibration by removing the stacker does not work Calibrating the reader by using the...

Page 11: ...y chip or disassemble the banknote reader Storage of patterns in flash memory allows you to update the information should a new banknote or a new forgery appear Pattern updating should be carried out...

Page 12: ...ower supply or the power supply is incorrect Check that power supply voltage is within limits Banknotes not fully accepted they are all rejected with a final strike of the stacker Stacker is full or t...

Page 13: ...MNP85ENV00 Rev 02 2014 01 07 Page 13 of 20 7 Appendix Figure 1 General view of the banknote reader...

Page 14: ...MNP85ENV00 Rev 02 2014 01 07 Page 14 of 20 Figure 3 Reader with Stacker 200 measures in mm Stacker 200 Stacker 375 Stacker 500 Figure 2 Possible stackers for BT11 banknote reader...

Page 15: ...MNP85ENV00 Rev 02 2014 01 07 Page 15 of 20 Figure 5 Reader with Stacker 500 measures in mm Figure 4 Reader with Stacker 375 measures in mm...

Page 16: ...Page 16 of 20 Figure 7 Image of the readers cover showing the MDB software and sensor software version In this case it is the 8 th version of the MDB software and the 3 rd version of the sensors Figur...

Page 17: ...MNP85ENV00 Rev 02 2014 01 07 Page 17 of 20 Figure 9 Tab to be pushed to clean the readers head Figure 8 Front view control card BT11 MDB...

Page 18: ...MNP85ENV00 Rev 02 2014 01 07 Page 18 of 20 Figure 10 Metal shaft to be pushed to remove stacker...

Page 19: ...________________________________________________________ ____________________________________________________________________ ____________________________________________________________________ _____...

Page 20: ...MNP85ENV00 Rev 02 2014 01 07 Page 20 of 20 JOFEMAR S A Reserves the right to introduce improvements in this model arising from its continuous research without prior notice...

Reviews: