SECTION 4 - MACHINE OPERATION
3121636
– JLG Lift –
4-17
•
To manually Level Down, turn the select switch counter
clockwise and hold until desired position is reached.
ONLY USE THE PLATFORM LEVELING OVERRIDE FUNCTION FOR SLIGHT
LEVELING OF THE PLATFORM. INCORRECT USE COULD CAUSE THE LOAD/
OCCUPANT TO SHIFT OR FALL. FAILURE TO DO SO COULD RESULT IN
DEATH OR SERIOUS INJURY.
Raise And Lower The Tower Boom
(Item 16, Figure 4-4.)
•
To raise the tower boom, depress the foot switch and
move the controller forward.
•
To lower the tower boom, depress the foot switch and
move the controller backwards.
Raise And Lower The Main Boom
(Item 17, Figure 4-4.)
•
To raise the main boom, depress the foot switch and
move the controller forward.
•
To lower the main boom, depress the foot switch and
move the controller backwards.
Telescope The Main Boom
(Item 18, Figure 4-4.)
•
To extend the main boom, depress the foot switch and
move the controller backward.
•
To retract the main boom, depress the foot switch and
move the controller forward.
Platform Rotation
(Item 19, Figure 4-4.)
•
To rotate the platform to the right, depress the foot-
switch and move the controller forward.
•
To rotate the platform to the left, depress the footswitch
and move the controller backwards.
Raise And Lower The Jib
•
To raise the jib, depress the foot switch and move the
controller forward.
•
To lower the jib, depress the foot switch and move the
controller backwards.
Swinging The Boom
WHEN SWINGING THE BOOM MAKE SURE THERE IS AMPLE ROOM FOR
THE BOOM AND UPRIGHT TO CLEAR SURROUNDING WALLS, PARTITIONS
AND EQUIPMENT.
ALSO WHEN SWINGING THE BOOM WITH WHEN THE BOOM IS LOWERED
BE CERTAIN THE BOOM/JIB/PLATFORM ARE HIGH ENOUGH TO AVOID
CONTACT WITH THE OUTRIGGERS.
•
To swing the boom to the right, depress the foot switch
and move the controller forward.
•
To swing the boom to the left, depress the foot switch
and move the controller backwards.
To