![JLG 1500SJ Operation And Safety Manual Download Page 76](http://html1.mh-extra.com/html/jlg/1500sj/1500sj_operation-and-safety-manual_2019999076.webp)
SECTION 4 - MACHINE OPERATION
4-8
– JLG Lift –
3121261
ALLOW ENGINE TO WARM-UP FOR A FEW MINUTES AT LOW SPEED BEFORE APPLYING
ANY LOAD.
4.
After engine has had sufficient time to warm up, shut engine
off.
5.
Turn Platform/Ground Select switch to the
Platform position.
6.
From the Platform, pull the Power/Emergency
Stop switch out.
7.
Push the Engine Start switch until engine
starts.
NOTE:
Footswitch must be in released (up) position before starter will
operate. If starter operates with footswitch in the depressed posi-
tion, DO NOT OPERATE MACHINE.
Shutdown Procedure
IF AN ENGINE MALFUNCTION CAUSES AN UNSCHEDULED SHUTDOWN, DETERMINE
THE CAUSE AND CORRECT IT BEFORE RESTARTING THE ENGINE.
1.
Remove all load and allow engine to operate at low speed
for 3-5 minutes; this allows further reduction of internal
engine temperature.
2.
Push Power/Emergency Stop switch in.
3.
Turn key of Platform/Ground Select switch to
the Off position.
Refer to Engine Manufacturer’s manual for detailed
information.
Summary of Contents for 1500SJ
Page 2: ......
Page 28: ...SECTION 1 SAFETY PRECAUTIONS 1 14 JLG Lift 3121261 NOTES ...
Page 68: ...SECTION 3 MACHINE CONTROLS AND INDICATORS 3 24 JLG Lift 3121261 NOTES ...
Page 100: ...SECTION 4 MACHINE OPERATION 4 32 JLG Lift 3121261 NOTES ...
Page 143: ...SECTION 5 LCD DISPLAY PANEL GENERATION 1 2 3121261 JLG Lift 5 43 Figure 5 29 BCS Lamp Screen ...
Page 149: ...SECTION 5 LCD DISPLAY PANEL GENERATION 1 2 3121261 JLG Lift 5 49 Figure 5 34 Swing DTC Screen ...
Page 166: ...SECTION 6 EMERGENCY PROCEDURES 6 4 JLG Lift 3121261 NOTES ...
Page 180: ...SECTION 7 ACCESSORIES 7 14 JLG Lift 3121261 NOTES ...
Page 208: ...SECTION 8 GENERAL SPECIFICATIONS OPERATOR MAINTENANCE 8 28 JLG Lift 3121261 NOTES ...
Page 212: ......
Page 213: ......