7) Risk to impact directly the sprinkler throw. When the machine will be started and the water will be supplied
to the machine, the throw can start suddenly and strong. It’s always better to release the flow partially till the
water pass through the sprinkler and then increase it smoothly till the normal working flow. Anyway be sure
nobody is next to the sprinkler when you start the machine.
8) Shock risk against plugs and couplings of the machine and the flex hose. Don’t open nor disconnect the plugs
and the couplings with the pressure inside. Be sure there’s no pressure before you release any plug or coupling.
9) Risk to impact against the oil of the hydraulic circuit (only in case of hydraulic options on the machine).
Don’t make anything to the hydraulic circuit if the pressure hasn’t been discharged through the quick couplings
or the distributor.
10) Risk of incidents on roads. Set up the sprinkler cart and the sprinkler in a way that the water throw will not
wet a transit area to avoid damages to persons and things.
9.0 SHIFTING OF MACHINES CONNECTED TO PRESSURISED MAIN LINES
When the machine has finished the cycle, pls reduce the pressure at the machine as follows:
1) Shut off the hydrant valve (where is connected the flex supply hose of the machine)
2) Manually open the small ball valve on the bottom collector and/or turbine
3) When the manometer indicates pressure “0” and there’s no more pressure in the flex supply hose
you can disconnect the couplings of flex supply hose and prepare and shift the machine to the next
position.