Rainstore

3

 Storm Drainage Detention & Exfiltration with Geotextile Fabric 

4

 

elevation more than 6mm (0.25 inches). All irregularities must be corrected and 
re-leveled. 

 

C.

 

Excavation must extend at least three feet beyond all sides of the Rainstore

placement area to allow ample room for product installation and sidefill 
compaction.  

 

D.

 

All inlet pipes and filtering systems should be installed to the edge of the 
excavated area per manufacturer’s recommendation. Please see section 5.10, for 
installation of connection pipes from these devices. 

 

E.

 

Typically, inlet pipes are located near or at the top of the Rainstore

chambers and 

outlet pipes (if necessary) are located along the bottom of the system. An 
overflow pipe should be located at the top of the system. 

 

5.2 Geogrid – First Layer:  

 

A.

 

Three separate layers of 
geogrid are required for 
the Rainstore

system.  

Geogrid arrives in rolls 
and can be shipped on a 
flatbed truck. Rolls are 
available in two sizes: 
9.84 ft x 164 ft roll that 
weighs 102 lbs, or 13.1 ft 
x 264 ft that weighs 138 
lbs.

 

This product is not 

supplied by Invisible 
Structures.

  

Two or more workers should carry the geogrid roll into the excavated 

area. 

 
B.

 

 Spread the first layer of geogrid at the base of the excavated area. The geogrid 
will quickly unroll across the excavation area. Seams of the geogrid should 
overlap at least 12 inches.  The first layer provides a stable and even surface for 
Rainstore

cell installation. 

  

C.

 

The geogrid layers may be temporarily anchored with rocks or adequate debris, to 
prevent it from rolling up before other system components can be installed. 

  

 

 
 
 
 
 

Summary of Contents for Rainstore3

Page 1: ...d CANNOT be planted directly above a complete Rainstore3 system The deep tree roots can damage the water storage capacity of the system by tearing the geotextile fabric and clogging Rainstore3 cells w...

Page 2: ...r installation instructions 3 Equipment Requirements A A powered lift to move stacked Rainstore3 cells into the excavated area A back hoe can have a fork or hanging chain attachment for lowering Rains...

Page 3: ...e requirements could result in breach of the product warranty 4 3 Inclement weather A Install Rainstore3 only if the outside air temperature is 55 degrees Fahrenheit or above The plastic becomes britt...

Page 4: ...An overflow pipe should be located at the top of the system 5 2 Geogrid First Layer A Three separate layers of geogrid are required for the Rainstore3 system Geogrid arrives in rolls and can be shipp...

Page 5: ...s should overlap 12 inches Seams can be joined with duct tape or a similar material to prevent shifting of the geotextile fabric C Be sure to leave excess fabric on all sides of the excavated area The...

Page 6: ...e paper divides the stacked cells remove and discard that as well E Final positioning of cells should be done by hand by at least two workers The cells are placed side by side with the grid side down...

Page 7: ...t will be welded in place Wipe away any dirt or dust particles The surfaces of the liner boot and the pipe must be completely clean and dry c Slide the boot sleeve on the pipe making sure the boot is...

Page 8: ...density Use a walk behind roller for small installations B For installations with an area of 1 000 square feet or more a light drivable roller such as the Bomag 125 D 4 that weighs 3 125 kgs 6890 lbs...

Reviews: