1

2

J

L
N
PE

J

Junction box

Heater

TS

Option AM

bn

bu

ye/gn

bk

gy

bn=brown bu=blue ye/gn=yellow/green bk=black gy=grey

Illustration 5: 

SL...THERM with TS

9

Commissioning

If the heater is installed in accordance with the notes in
the 

Installation  [

}

Page  4]

  section  and 

Connection  [

}

Page  5]

  sections,  then  the  radiator  may  be  commis-

sioned.

 CAUTION

Sufficient heat dissipation must be ensured.

Unauthorized covers must be removed as otherwise
there is the risk of the heater overheating.

The heating circuit is permanently disconnected by a
temperature melt fuse which can't be reset if these in-
stallation instructions are not adhered to.

10

Maintenance

The design of the device does not require any mainten-
ance.

Functional  and  safety  test  intervals  can  be  freely  selec-
ted  by  the  operator  in  accordance  with  the  applicable
regulations.

Repairs  may  only  be  carried  out  by  the  manufacturer  in
the factory.

All  components  have  to  be  kept  clean  and  free  of  dust
and  harmful  substances  that  could  lead  to  excessive
temperature rise.

In  the  dust  Ex  area,  the  applicable  requirements  of  EN
60079-17 and EN 60079-19 must be complied with.

11

Troubleshooting

If the heater fails, check the installation. Carry out a con-
tinuity  test  on  the  heating  circuit.  Pay  attention  to  the
connection  diagram  and  switching  point  of  the  thermo-
stat!

12

Deinstallation

Disassembly  may  only  be  carried  out  by  a  trained  per-
son.

 DANGER

Risk of fatal injury from electric current!

If contact is made with live components, there is the risk
of fatal injury.

For this reason, switch off the voltage supply, secure
against being switched on again and check that no more
voltage is present.

Disconnect connection line from the clamps and from the
connection  socket,  disconnect  device  from  bracket  and
remove it.

13

Disposal

Disassemble  the  components  of  the  product,  taking  the
applicable local labour protection and environmental reg-
ulations into consideration and make sure that the com-
ponents are recycled:

• Scrap metal

• Send plastic elements to recycling

• Sort other components according to their material

properties and dispose of them.

Summary of Contents for SL MULTITHERM D.A

Page 1: ...Operating Instructions SL MULTITHERM D A HOM499575435Ien 6 03 02 2020 ...

Page 2: ...f contents 1 General 3 2 Use 3 3 Explanation of symbols for warnings and signal words 3 4 Safety information 3 5 Installation accessories 4 6 Technical Data 4 7 Installation 4 8 Connection 5 9 Commissioning 7 10 Maintenance 7 11 Troubleshooting 7 12 Deinstallation 7 13 Disposal 7 14 EU declaration of conformity 8 15 Further information and service 8 ...

Page 3: ...on necting cable If a TAE is used the respective operating instructions must be complied with EC type examination certificates PTB 02 ATEX 1116 X with appendices and supplements in German and Eng lish as well as IEC Scheme Certificate IECEX PTB 07 0055X See http www intertec info 3 Explanation of symbols for warnings and signal words The safety information warns the user about risks and provide in...

Page 4: ...lts 2 T head bolt type 28 15 M 6x15 4 M6 flat square nut 2 Washer shape A 6 4 4 Lock washers shape J 6 4 2 M6 hex nut If one of the components listed here is not included in the scope of delivery then please contact the manufac turer 6 Technical Data Protection class IP66 IP68 1bar 30min Rated voltage max 265 V AC Permitted operating voltage max 275 V AC Rated current in compli ance with VDE 0298 ...

Page 5: ...the per missible bending radius 5 x outer diameter into consid eration In the dust Ex area the applicable requirements of EN 60079 14 must be complied with Illustration 2 Installation example MULTITHERM with TAE or TS and clearance Additional installation material such as rails or panels and also junction boxes are not included in the standard scope of delivery see Installation accessories Page 4 ...

Page 6: ...an IT system an insulation monit oring device needs to be used which switches off the supply as soon as the insulation resistance is no greater than 50 Ω per Volt of the rated voltage refer also to DIN EN 60079 14 section 7 4 ATTENTION Never remove the adapter cable gland Illustration 3 Example heater with KLE connection CAUTION NOTICE Do not remove adapter cable connec tion to connect up the heat...

Page 7: ...ied out by the manufacturer in the factory All components have to be kept clean and free of dust and harmful substances that could lead to excessive temperature rise In the dust Ex area the applicable requirements of EN 60079 17 and EN 60079 19 must be complied with 11 Troubleshooting If the heater fails check the installation Carry out a con tinuity test on the heating circuit Pay attention to th...

Page 8: ...N IEC 60079 1 2014 EN IEC 60079 31 2014 EN IEC 61000 6 4 2007 A1 2011 Harmonized Standard RoHS DIN EN IEC 63000 2019 Designation 0102 II 2 G Ex db IIC T6 T5 T4 T3 Gb II 2 D Ex tb IIIC T85 C T100 C T135 C T200 C Db PTB 02 ATEX 1116 X Neustadt January 28th 2020 Dipl Ing Martin Hess Managing Director 15 Further information and service If the information contained in this instruction manual should not...

Reviews: