Figure 33: Preparing FlexZone sensor cable steps 3 & 4
5. Trim back the clear tube to a length of 5 mm by carefully removing app. 15
mm from the end of the cable. DO NOT nick the center conductor.
6. Bend and form the two sections of twisted braided shield into conductors that
are parallel with, and separated from, the center conductor by 5 mm on
opposite sides of the cable.
Figure 34: Preparing FlexZone sensor cable steps 5 & 6
Note:
For cable splices proceed to "Sensor cable splices" on page 33. For
terminations proceed to "Sensor cable terminations" on page 36.
Processor connections
See "Cable preparation (all connections)" on page 31 for steps 1 to 6.
7. Trim the twisted braided shields and the center conductor to a length of 6 mm
past the end of the clear tube.
8. Remove the A Side terminal block from T9. Connect the A Side cable to the
three position terminal block by inserting the center conductor and the two
twisted braided shield conductors into the terminal block and tightening the
screws. The center conductor goes into the center (second) terminal.
Summary of Contents for FlexZone Series
Page 1: ...FlexZone Product Guide P N 466 2877 REV C ISS 19MAR19...
Page 6: ......
Page 24: ......
Page 41: ...Chapter 2 Installation FlexZone Product Guide 35 Figure 40 Mounting the splice enclosure 15 cm...
Page 62: ......
Page 86: ......
Page 94: ......