STEP EIGHT: Final slide position.
It is essential that the slide be in its correct horizontal and vertical position prior to pouring
concrete; and since the pool cannot be moved, start checking position with the exit section
first. Starting with and then ensuring that the exit section is installed correctly is absolutely
necessary for a successful installation.
The exit section must meet the pool edge at the correct elevation, in the correct orientation
and be level in both axes. (Fig. 15 & Fig. 16) When determining level position for the exit
section please note that the exit section starts with a 15° up slope, which then makes a
gradual transition to level point toward the exit point. Check for level position only as illustrated
below.
Utilize an angle finder along the centerline of the flume ensure the flume is at the correct angle.
Check the angle along the centerline of the flume only. (Fig. 17) Do not check angle on up
or down wedge as the slope transitions through them.
Fig. 17
Fig. 15
Fig. 16