5.0 Circuit Breaker Racking Instructions
1. Connect the required accessories to the inoRAC by following the accessory
instructions.
2. Connect the inoRAC to an adequate power source via the receptacle on the
side of the control enclosure.
3. Turn on the inoRAC by placing the ON/OFF switch on the side of the control
enclosure into the “ON” position. For UPS/Battery units follow steps in section
4.0
above.
4. Start the inoRAC by pressing the “Racking Unit Control” button on the Operator
Panel.
5. Ensure the inoRAC is not connected to a circuit breaker. Ensure the inoRAC
is free to operate all accessories. Follow the Operator Panel instructions for
calibrating the inoRAC.
6. Select the operation to be performed, “Rack Breaker” on the Operator Panel.
7. Follow the Operator Panel instructions for selecting the breaker to be racked.
8. Confirm the object circuit breaker is open position via a visual inspection.
9. Adjust the inoRAC height to the level of the circuit breaker racking mechanism
via the “Raise” and “Lower” buttons on the Operator Panel.
10. Align the inoRAC breaker connection accessory to the circuit breaker racking
mechanism via the “Jog CW” and “Jog CCW” buttons on the Operator Panel.
11. Connect the inoRAC to the circuit breaker racking mechanism.
12. Set the brakes on the inoRAC.
13. Move to a safe location outside the arc flash hazard boundary with the Operator
Panel.