Appendix A – Using the CT01 Commissioning Tool
A-2.2 Connecting to Sub System Gateway (IG01)
When you connect the CT01 to the Innotech Sub System Gateway (IG01) using the provided adaptor
cable, the CT01 can communicate with all subsystem controllers on that network that are connected
to the IG01, as illustrated in Figure A-2 below.
Figure A-2:
Connecting the CT01 to a Sub System Gateway IG01
The subsystem network must be reconnected as it was before once the commissioning process is complete.
NOTE
Summary of Contents for MAXIM 1010
Page 1: ...MAXIM Series Controllers INSTALLATION INSTRUCTIONS...
Page 9: ...Chapter 1 Preliminary Information MAXIM Series Controllers INSTALLATION INSTRUCTIONS...
Page 15: ...MAXIM Series Controllers INSTALLATION INSTRUCTIONS Chapter 2 Mechanical Installation...
Page 23: ...Chapter 3 Electrical Installation MAXIM Series Controllers INSTALLATION INSTRUCTIONS...
Page 41: ...Chapter 4 Network Installation MAXIM Series Controllers INSTALLATION INSTRUCTIONS...
Page 43: ...Chapter 5 Commissioning MAXIM Series Controllers INSTALLATION INSTRUCTIONS...