NOISE EMISSION
32
A. Compressed Air Leaks
Correct all compressed air leaks during the first shutdown period after discovery. If severe
enough to cause serious noise problems and efficiency loss, shut down immediately and
correct the leak(s).
B. Safety and Control Systems
Repair or replace all safety and control systems or circuits as malfunction occurs. No
compressor should be operated with either system bypassed, disabled, or nonfunctional.
C. Acoustic Materials
In daily inspections, observe these materials. Maintain all acoustic material as nearly as
possible in its original condition. Repair or replace all sections that have: 1) sustained damage,
2) have partially separated from panels to which they were attached, 3) are missing, or have
otherwise deteriorated due to severe operating or storage conditions.
D. Fasteners
All fasteners such as hinges, nuts, bolts, clamps, screws, rivets, and latches should be
inspected for looseness after each 100 hours of operation. They should be retightened,
repaired, or if missing, replaced immediately to prevent subsequent damage and noise
emission increase.
E. Enclosure Panels
Enclosure panels should also be inspected at 100 hour operational intervals. All panels that
are warped, punctured, torn, or otherwise deformed, such that their noise containment
function is reduced, should be repaired or replaced before the next operation interval. Doors,
access panels, and hatch closures especially, should be checked and adjusted at this time to
insure continuous seating between gasket or acoustic material and the mating frame.
F. Air Intake and Engine Exhaust
Engine and compressor air intake and engine exhaust systems should be inspected after each
100 hours of operation for loose, damaged, or deteriorated components. Repairs or
replacements should be made before the next period of use.
G. Cooling Systems
All components of the cooling system for engine water and compressor oil should be inspected
Maintenance Schedule
Item
Area
Period
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
Compressed Air Leaks
Safety and Control Systems
Acoustic Materials
Fasteners
Enclosure Panels
Air Intake & Engine Exhaust
Cooling Systems
Isolation Mounts
Engine Operation
Fuels & Lubricants
As Detected
As Detected
Daily
100 hours
100 hours
100 hours
250 hours
250 hours
See Operator’s Manual
See Operator’s Manual
Summary of Contents for P185AWIR
Page 6: ...1 4...
Page 7: ...3 FOREWORD...
Page 8: ...4...
Page 10: ...6...
Page 11: ...7 DRAWBAR NOTICE...
Page 12: ...Operating Maintenance Manual 8...
Page 14: ...Operating Maintenance Manual 10...
Page 15: ...11 Section 1 Safety...
Page 19: ...Safety Operating Maintenance Manual 15...
Page 20: ...Operating Maintenance Manual Safety 16...
Page 22: ...Operating Maintenance Manual Safety 18...
Page 23: ...Safety Operating Maintenance Manual 19...
Page 25: ...21 Section 2 WARRANTY...
Page 30: ...Operating Maintenance Manual WARRANTY 26...
Page 32: ...Operating Maintenance Manual WARRANTY 28...
Page 33: ...29 Section 3 NOISE EMISSION...
Page 39: ...35 Section 4 GENERAL DATA...
Page 42: ...Operating Maintenance Manual GENERAL DATA 38...
Page 43: ...39 SECTION 5 OPERATION...
Page 51: ...47 Section 6 MAINTENANCE...
Page 59: ...55 Section 7 LUBRICATION...
Page 61: ...57 Section 8 Trouble Shooting...