Chapter 2: Installation
26
NS3562-8P-2S-V2 Industrial Managed Switch User Manual
Wall mount plate mounting
Note:
Follow all the wall mount plate installation steps as shown in the example.
To install the industrial managed switch on the wall:
1. Drill four 8 mm diameter holes in the wall, with a horizontal distance of 163 mm
between each.
2. Install a conductor pipe inside the board hole and flush the edge of the conductor
pipe with the wall surface.
3. Screw the bolts into the conductor pipe. The switch is between the bolts and the
conductor pipe, as shown below.
To install the industrial managed switch on a magnetic surface: