15
Mexico Super 100 FF & 125 FF -
Installation
INSTALLATION
SIDE FLUE OUTLET
1.
The boiler turret assembly is factory built for rear flue
installation.
2.
Remove the turret access cover.
3.
Remove the sealing plate from the appropriate side to
be used and refit in the rear outlet.
17 SIDE FLUE ASSEMBLY - Exploded view
For wall thickness 114mm to 600mm
6.
Elbow.
7.
Side outlet plate.
8.
Flue connector.
9.
Sealing plate.
10.
Turret access cover.
LEGEND
1.
Terminal.
2.
Weather seal.
3.
Flue assembly.
4.
Boiler sealing ring.
5.
Flue extension tube (medium with ring).
4.
An optional flue duct extension kit is required for lengths
(distance from the outside wall to the relevant side of
the boiler casing) greater than 600mm (23
1/2
") Refer to
Frame 7.
5.
When cutting the ducts always use the cardboard
support provided.
18 PREPARING THE WALL
1.
Tape the template into the selected
position.
2.
Mark onto the wall the position of the
flue duct hole.
IMPORTANT.
Ensure that, during the
cutting operation, masonry falling outside
of the building does not cause damage
or personal injury.
3.
Cut the flue hole, preferably with a
125mm (5") core boring tool,
ensuring that the hole is square to
the wall. If the hole has been quite
accurately cut with a drill then making
good the wall faces is not essential
as seals are provided at both ends of
the flue. However, both wall faces
immediately around the cut hole
should be flat; make good if
necessary. For less accurate holes
make good to approximately 125mm
(5") diameter at the 2 wall faces.
Note.
If the
terminal is to be
sited within 25-
40mm of a
corner or
vertical pipe
(refer to Table
3) then the hole
MUST be
accurately cut
and the rubber
weather seal
trimmed around
the groove
provided.
The terminal
wall plate need
not be fitted.