Model VIP+
8
Owner's Manual
Joint Assembly – Low temperature (600°F Max) Applications
Figure 1
Step 1
: Apply one bead of X-TRASIL HD #4706-3 red silicone on the male end of the flue just under the formed bead.
Step 2
: Slip the top chimney male end into the expanded side of the lower chimney. Refer to chimney label for flue gases direction.
Step 3
: Assemble the flue locking band and secure by tightening the bolt . Do not remove the excess of sealant.
Step 4
: Install locking band insulation strip around the joint. (if applicable)
Step 5
: Install exterior casing locking band. Secure by tightening the 2 bolts.
Step 6
: Apply a bead of exterior sealant (see
Table 4
and
5C
) on the upper joint of the casing locking band (to prevent water infiltrations for outside
applications only)
Figure 2
Figure 3